Armadale Wind Farm (43.2 MW)

Armadale Wind Farm is a 43.2 MW wind farm project in Highland, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application withdrawn on 7 May 2024; the record was last updated on 11 July 2024. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

43.2 MWwind farm
application withdrawnstatus in REPD
11 July 2024record last updated
Highlandcouncil area

Planning timeline

DateStage
22 March 2022Application submitted
7 May 2024Application withdrawn

Project details

Technology
wind farm
Capacity
43.2 MW
Status (REPD)
application withdrawn
Record last updated
11 July 2024
Operator or applicant
Brookfield Renewable UK
Planning authority
Scottish Government (S36)
Planning application reference
ECU00003455
Turbines
9
Turbine height
150 m
Address (REPD)
Land 1100M South Of, Armadale Farm, Armadale, Thurso,
Council area (by location)
Highland
REPD reference
6362

The scheme also includes 42 MW of battery storage, recorded separately in REPD (application withdrawn).

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Loch Toftingall, Halsary Wind Farmbattery storage49.9approved, not built2.2
Strathy Northwind farm67.7operational5.6
Cairnview, Bettyhillwind farm48approved, not built5.9
Phase 1 Bettyhill Wind Farmwind farm5operational6.8
Strathy Woodwind farm62.4under construction7.6
Melvich Wind Energy Hubwind farm57.6application submitted9.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (58.5347, -4.0769).