Energy Projects Near You

The Manor of Cadland Estate (5 MW solar farm)

The Manor of Cadland Estate is a 5 MW solar farm project in New Forest, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 23 July 2012; the record was last updated on 20 February 2014.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
20 February 2014record last updated
New Forestcouncil area

Planning timeline

DateStage
21 January 2011Application submitted
17 May 2011Planning permission granted
22 May 2012Construction started
23 July 2012Operational

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
20 February 2014
Operator or applicant
The Manor of Cadland Estate
Planning authority
New Forest
Planning application reference
11/96086
Site area
12.0 ha
Address (REPD)
Whitefield Farm, Langley
Council area (by location)
New Forest
Time to decision
17 weeks
REPD reference
1562

Who decides

ApplicationsNew ForestUK
Decided applications (solar, wind, battery)2610,236
Refused7 (27%)19%
Solar refused6 of 2212%
Battery storage refused1 of 416%
Median time from submission to decision11.0 weeks17.0 weeks
Appeals lodged / allowed2 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Exbury Solar Farmsolar farm5refused on appeal1.8
Hamble Lane Battery Energy Storagebattery storage6approved, not built8.4
Netley Landfill Solarsolar farm12operational9.7
Weston Lanebattery storage49.9refused9.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.8051, -1.3603).