Energy Projects Near You

Solar, wind and battery projects near Birmingham (B18)

93 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of B18 (Birmingham): 5 are waiting for a planning decision, 81 approved but not yet running, 3 operational. The largest live scheme is Edwin Richards Quarry, Portway Road (100 MW battery storage, approved on 12 February 2025, not yet built), 8.3 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

93projects within 10 km
5awaiting a decision
81approved, not running
3operational

Projects within 10 km of B18

Projects of 1 MW and more (13)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
DPD Distribution Centrerooftop solarrooftop solar1operationalupdated Feb 2017Nov 2015granted Dec 2015Feb 2017Sandwell5.9
Broadwell Roadrooftop solarrooftop solar1approved, not builtupdated Jun 2022May 2022granted Oct 2022Jun 2022Sandwell5.9
Fort Shopping Park, Fort Parkwayrooftop solarrooftop solar1.6approved, not builtupdated Oct 2023Aug 2023granted Sep 2023Oct 2023Birmingham7.2
Bustleholme Substationbattery storagebattery storage49.9operationalupdated Oct 2023Jul 2020granted Feb 2021Oct 2023Sandwell7.2
Fordhouse Lanebattery storagebattery storage20approved, not builtupdated Oct 2024Jan 2023granted Aug 2023Oct 2024Birmingham7.5
Chapel Lanebattery storagebattery storage49.4approved, not builtupdated Jan 2025Oct 2023granted Jan 2025Jan 2025Walsall7.9
Edwin Richards Quarry, Portway Roadbattery storagebattery storage100approved, not builtupdated Feb 2025Nov 2024granted Feb 2025Feb 2025Sandwell8.3
Mucklow Hillbattery storagebattery storage12permission expiredupdated Jan 2022Oct 2017granted Dec 2017Jan 2022Dudley8.7
Midland Quarry Products, Smith Roadbattery storagebattery storage10approved, not builtupdated Feb 2025May 2024granted Jan 2025Feb 2025Sandwell9.1
Golds Hillbattery storagebattery storage57operationalupdated Oct 2025May 2021granted Aug 2021Oct 2025Sandwell9.2
Lowlands Farmbattery storagebattery storage50approved, not builtupdated Sep 2024Nov 2022refused Sep 2023Sep 2024Dudley9.5
Illeybrook Farmbattery storagebattery storage99.8approved, not builtupdated Feb 2025Jul 2023granted Feb 2025Feb 2025Dudley9.8
Illey Lanebattery storagebattery storage70approved, not builtupdated Nov 2025Sep 2024granted Oct 2025Nov 2025Bromsgrove9.9
Smaller schemes under 1 MW, mostly rooftop solar (60)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Cambrian Wharf, Brindley Drive - Student Accommodationrooftop solarrooftop solar0.2approved, not builtupdated May 2026Nov 2023granted Jan 2026May 2026Birmingham1.6
New Summer Street, Hockleybattery storagebattery storage—approved, not builtupdated Dec 2023Oct 2023granted Feb 2024Dec 2023Birmingham1.7
Ash And Lacy, Alma Street - Photovoltaic Solar Panelsrooftop solarrooftop solar0.2approved, not builtupdated Nov 2024Sep 2024granted Oct 2024Nov 2024Sandwell1.7
Betel of Britain, Chester Streetrooftop solarrooftop solar—approved, not builtupdated Apr 2026Dec 2025granted Feb 2026Apr 2026Birmingham2.6
First Steps Nursery, Waterloo Roadrooftop solarrooftop solar0.3approved, not builtupdated Feb 2024Dec 2023granted Feb 2024Feb 2024Sandwell2.8
Big Yellow Self Storage, Adams Streetrooftop solarrooftop solar0.2application submitted may be out of dateupdated Sep 2022Sep 2022—Sep 2022Birmingham2.9
Holyhead Roadrooftop solarrooftop solar0.4application submittedMay 2026——Birmingham2.9
Holyhead Road - Roof Mounted Solar PV solar panelsrooftop solarrooftop solar0.2approved, not builtupdated Aug 2024Jun 2024granted Jul 2024Aug 2024Birmingham2.9
Oxford Road - Micro Energy Storage Facilitybattery storagebattery storage0.2refusedupdated Sep 2025Jul 2025refused Sep 2025Sep 2025Sandwell2.9
JJ Foodservice Limited, Avenue Roadrooftop solarrooftop solar0.5approved, not builtupdated Aug 2023Jul 2023granted Aug 2023Aug 2023Birmingham3.0
Guru Nanak Gurdwara, High Streetrooftop solarrooftop solar0.2approved, not builtupdated Nov 2024Sep 2024granted Nov 2024Nov 2024Sandwell3.2
West Bromwich Albion Football Clubrooftop solarrooftop solar0.7approved, not builtupdated Sep 2025Jul 2025granted Sep 2025Sep 2025Sandwell3.2
National Express Perry Bar Bus Depot, Aston Lanerooftop solarrooftop solar0.3approved, not builtupdated Aug 2024Jun 2024granted Aug 2024Aug 2024Birmingham3.3
Lansing Linde Creighton Limited, Dartmouth Roadrooftop solarrooftop solar0.2approved, not builtupdated Jan 2026Nov 2025granted Jan 2026Jan 2026Sandwell3.4
Heartlands Academy, Great Francis Streetrooftop solarrooftop solar0.2approved, not builtupdated Aug 2023Jul 2023granted Aug 2023Aug 2023Birmingham3.4
Perry Barr Bus Depot, Wellhead Roadrooftop solarrooftop solar0.2approved, not builtupdated Sep 2023Jul 2023granted Sep 2023Sep 2023Birmingham3.5
Estone Drive, Astonsolar farmsolar farm0.3approved, not built may be out of dateupdated Aug 2023Jun 2023granted Jul 2023Aug 2023Birmingham3.7
Devonshire Infant & Junior Academies, Auckland Roadrooftop solarrooftop solar0.3approved, not builtupdated Aug 2025Jun 2025granted Jul 2025Aug 2025Sandwell3.7
Lun Cheung Enterprise Limitedrooftop solarrooftop solar0.3approved, not builtupdated Jul 2023May 2023granted Jun 2023Jul 2023Birmingham3.8
Lun Cheung Enterprise Limitedrooftop solarrooftop solar0.2approved, not builtupdated Jul 2023May 2023granted Jun 2023Jul 2023Birmingham3.8
Dollman Street - Roof Mounted Solar PV Systemsrooftop solarrooftop solar0.4approved, not builtupdated Jul 2024May 2024granted Jul 2024Jul 2024Birmingham3.8
Grosvenor Roadrooftop solarrooftop solar0.3approved, not builtupdated Feb 2025Dec 2024granted Feb 2025Feb 2025Birmingham3.8
Prince Albert High Schoolrooftop solarrooftop solar0.1approved, not builtupdated Feb 2026Nov 2025granted Dec 2025Feb 2026Birmingham4.0
Network Park Industrial Estate, Duddeston Mill Roadrooftop solarrooftop solar0.2approved, not builtupdated Jun 2026Mar 2026granted Apr 2026Jun 2026Birmingham4.2
Industrial Park, Electric Avenuerooftop solarrooftop solar0.4approved, not builtupdated Feb 2026Nov 2025granted Dec 2025Feb 2026Birmingham4.3
Hamstead Hall Community Learning Centre, Craythorne Avenuerooftop solarrooftop solar0.4application submittedApr 2026——Birmingham4.4
Morrisons, Coventry Roadrooftop solarrooftop solar0.3approved, not builtupdated May 2025Mar 2025granted Apr 2025May 2025Birmingham4.4
Altitude, Deykin Avenuerooftop solarrooftop solar—approved, not built may be out of dateupdated Nov 2022Sep 2022granted Oct 2022Nov 2022Birmingham4.5
Tameside Drive, Holford Industrial Estaterooftop solarrooftop solar1approved, not builtupdated Jan 2024Feb 2023granted Apr 2023Jan 2024Birmingham4.5
Stargate Business Park, Cuckoo Road, Unit 2rooftop solarrooftop solar0.1approved, not builtupdated Apr 2026Jan 2026granted Feb 2026Apr 2026Birmingham4.7
Gravelly Industrial Park, Units 59 & 60rooftop solarrooftop solar0.3approved, not builtupdated May 2024Apr 2024granted May 2024May 2024Birmingham5.1
Tat Bank Road, Western Road - Micro Energy Storagebattery storagebattery storage0.2approved, not builtupdated Sep 2025Jul 2025granted Sep 2025Sep 2025Sandwell5.5
Golden Hillock Road, Sparkbrookrooftop solarrooftop solar0.7approved, not builtupdated Feb 2024Dec 2023granted Feb 2024Feb 2024Birmingham5.6
North Birmingham Academy, College Roadrooftop solarrooftop solar0.2approved, not builtupdated Aug 2023Jul 2023granted Aug 2023Aug 2023Birmingham5.7
Eden Boys Leadership Academy, Alum Rock Roadrooftop solarrooftop solar—approved, not builtupdated Aug 2023May 2023granted Aug 2023Aug 2023Birmingham5.7
Selly Park Girls School, Selly Park Roadrooftop solarrooftop solar0.3approved, not builtupdated Jun 2026Mar 2026granted Apr 2026Jun 2026Birmingham5.9
Voestalpine Metsec, Broadwell Roadrooftop solarrooftop solar0.7approved, not builtupdated May 2024Apr 2024granted May 2024May 2024Sandwell5.9
Lewis Road, Perry Hill Lane Energy Storage Facilitybattery storagebattery storage0.2refusedupdated Sep 2025Jul 2025refused Sep 2025Sep 2025Sandwell6.1
Barr View Primary And Nursery Academy, Aldridge Road Solar PV Systemsrooftop solarrooftop solar0.2approved, not builtupdated May 2024Apr 2024granted May 2024May 2024Birmingham6.1
Greet Primary School, Percy Roadrooftop solarrooftop solar0.2approved, not builtupdated Jul 2024May 2024granted Jul 2024Jul 2024Birmingham6.2
Cole Valley, Westwood Avenuerooftop solarrooftop solar0.8approved, not builtupdated Apr 2023Mar 2023granted Apr 2023Apr 2023Birmingham6.6
Mercedes benz garage, Bromford Lanerooftop solarrooftop solar0.3approved, not builtupdated May 2023Feb 2023granted Mar 2023May 2023Birmingham6.6
York Road - Micro Energy Storage Facilitybattery storagebattery storage0.2approved, not builtupdated Jun 2026Mar 2026granted May 2026Jun 2026Sandwell6.8
Formans Road, Tyseleyrooftop solarrooftop solar0.3approved, not builtupdated May 2023Feb 2023granted Apr 2023May 2023Birmingham6.8
Birmingham Heartlands Hospital - Roof Top Solar Farmrooftop solarrooftop solar0.6approved, not builtupdated Jul 2022Jun 2022granted Oct 2022Jul 2022Birmingham6.8
Wolverhampton Road - Micro Energy Storage Facilitybattery storagebattery storage—approved, not builtupdated Nov 2025Aug 2025granted Oct 2025Nov 2025Sandwell6.9
Greets Green Playing Field, Wattle Roadbattery storagebattery storage0.2approved, not builtupdated Jun 2025Feb 2025granted May 2025Jun 2025Sandwell6.9
Bull Lane - Micro Energy Storagebattery storagebattery storage0.2application submittedupdated May 2026Apr 2026—May 2026Sandwell7.0
Charlemont Open Space, Charlemont Road - Micro Energy Storagebattery storagebattery storage0.2approved, not builtupdated Jun 2026Mar 2026granted May 2026Jun 2026Sandwell7.0
Ridgacre Enterprise Park, Ridgacre Road - Micro Energy Storage Facilitybattery storagebattery storage0.2approved, not builtupdated May 2025Feb 2025granted Apr 2025May 2025Sandwell7.0
David Lloyd Leisure Centre, Shady Lanerooftop solarrooftop solar0.3approved, not builtupdated Apr 2024Feb 2024granted Mar 2024Apr 2024Birmingham7.1
Farrow Road Industrial Estate, Farrow Roadrooftop solarrooftop solar0.2approved, not builtupdated May 2023Feb 2023granted Apr 2023May 2023Birmingham7.2
Oldbury Roadrooftop solarrooftop solar0.7approved, not builtupdated Dec 2022Nov 2022granted Dec 2022Dec 2022Sandwell7.2
Parfetts Cash and Carry, Redfern Roadrooftop solarrooftop solar0.4approved, not builtupdated Jan 2025Nov 2024granted Dec 2024Jan 2025Birmingham7.3
Tesco Stores, Coleshill Roadrooftop solarrooftop solar0.3approved, not builtupdated Feb 2025Dec 2024granted Feb 2025Feb 2025Birmingham7.3
Emr Oldbury, Union Roadrooftop solarrooftop solar1approved, not builtupdated Jan 2025Apr 2024granted Jun 2024Jan 2025Sandwell7.4
Shenley Court Secondary School, Shenley Lanerooftop solarrooftop solar0.2approved, not builtupdated Aug 2023Jul 2023granted Aug 2023Aug 2023Birmingham7.7
Bell Heath Way, Woodgaterooftop solarrooftop solar0.6approved, not builtupdated Mar 2023Jan 2023granted Feb 2023Mar 2023Birmingham7.8
Ormiston Sandwell Community Academy, Lower City Roadrooftop solarrooftop solar0.3approved, not builtupdated Mar 2026Nov 2025granted Jan 2026Mar 2026Sandwell8.0
Tansun Limited, Spectrum Houserooftop solarrooftop solar0.2approved, not builtupdated Nov 2022Oct 2022granted Nov 2022Nov 2022Sandwell8.1

20 more projects not listed (furthest or smallest).

Distance from the average position of the B18 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm101000.3
Rooftop solar694641024.4
Battery storage2311622401

MW in pipeline: pending, approved and under-construction capacity.

How Birmingham decides solar, wind and battery applications

ApplicationsBirminghamUK
Decided applications (solar, wind, battery)5110,236
Refused1 (2%)19%
Solar refused1 of 4712%
Battery storage refused0 of 416%
Median time from submission to decision6.9 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

UK: all UK planning authorities. Counted under these REPD planning authority names: Birmingham, Birmingham Ladywood.

All projects in Birmingham

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near B18, 5 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.