Solar, wind and battery projects near Cardiff (CF24)
41 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of CF24 (Cardiff): 5 are waiting for a planning decision, 24 approved but not yet running, 9 operational. The largest live scheme is Rover Way, Splott Energy Park & Data Centre (1,000 MW battery storage, approved on 15 April 2025, not yet built), 2.5 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of CF24
Projects of 1 MW and more (20)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Ipswich Road, Cardiffbattery storage | battery storage | 93 | approved, not builtupdated Apr 2024 | Dec 2023 | granted Apr 2024 | Apr 2024 | Cardiff | 1.6 |
| Principality Stadium, Westgate Streetrooftop solar | rooftop solar | 1.5 | operational | Aug 2025 | granted Sep 2025 | — | Cardiff | 1.8 |
| Rover Way, Splott Energy Park & Data Centrebattery storage | battery storage | 1,000 | approved, not builtupdated May 2025 | Mar 2024 | granted Apr 2025 | May 2025 | Cardiff | 2.5 |
| Lamby Way Solar Farmsolar farm | solar farm | 8.9 | operationalupdated Jan 2021 | Feb 2019 | granted May 2019 | Jan 2021 | Cardiff | 2.6 |
| Aldi - Cardiffrooftop solar | rooftop solar | 1.5 | operationalupdated Nov 2017 | — | — | Nov 2017 | Cardiff | 3.3 |
| G24 Innovations Turbinewind turbine | wind turbine | 2.3 | operationalupdated Aug 2011 | Sep 2007 | granted Jan 2008 | Aug 2011 | Cardiff | 4.5 |
| Panasonic Manufacturing, Pentwynbattery storage | battery storage | 1.1 | under constructionupdated Feb 2025 | Apr 2024 | granted Jun 2024 | Feb 2025 | Cardiff | 4.7 |
| Euroclad Group, Wentloog Roadrooftop solar | rooftop solar | 1 | approved, not builtupdated Apr 2026 | Jan 2026 | granted Mar 2026 | Apr 2026 | Cardiff | 5.1 |
| Brynwell Farmsolar farm | solar farm | 21 | approved, not builtupdated Feb 2026 | Apr 2021 | granted Nov 2022 | Feb 2026 | Cardiff | 5.4 |
| Woden Parksolar farm | solar farm | 5 | operationalupdated Aug 2014 | Dec 2012 | granted Mar 2013 | Aug 2014 | Cardiff | 6.1 |
| Coal Pit Lanesolar | solar | 5.3 | application withdrawnupdated Nov 2014 | Jun 2014 | — | Nov 2014 | Newport | 7.9 |
| Newport (Began Road)solar farm | solar farm | 4.9 | operationalupdated Feb 2017 | Apr 2014 | granted Oct 2015 | Feb 2017 | Newport | 8.2 |
| Biglis Farmsolar farm | solar farm | 5 | operationalupdated Jul 2016 | May 2015 | granted Oct 2015 | Jul 2016 | Vale of Glamorgan | 9.0 |
| Vianshill Farm, Parc Dyffryn Solar Farm & Battery Storagesolar farm | solar farm | 65 | approved, not builtupdated Feb 2026 | Oct 2022 | granted May 2024 | Feb 2026 | Vale of Glamorgan | 9.1 |
| Home Farmsolar farm | solar farm | 3 | operationalupdated Jun 2017 | Jul 2015 | granted Jan 2016 | Jun 2017 | Vale of Glamorgan | 9.2 |
| Pen Y Maes, Ashby Roadbattery storage | battery storage | 50 | refusedupdated Jun 2025 | Oct 2024 | refused May 2025 | Jun 2025 | Vale of Glamorgan | 9.4 |
| Wentlooge Renewable Energy Hubsolar farm | solar farm | 125 | appeal lodged may be out of dateupdated Feb 2024 | Jun 2022 | — | Feb 2024 | Newport | 9.4 |
| Sully Moors Roadbattery storage | battery storage | 50 | approved, not builtupdated Mar 2026 | Aug 2025 | granted Feb 2026 | Mar 2026 | Vale of Glamorgan | 9.6 |
| Clearwell Farm solarsolar farm | solar farm | 2 | operationalupdated Sep 2016 | Apr 2011 | granted May 2011 | Sep 2016 | Newport | 9.6 |
| Momentive Speciality Chemicals, Sully Moors Roadsolar farm | solar farm | 1.3 | approved, not builtupdated Aug 2023 | Apr 2023 | granted Jul 2023 | Aug 2023 | Vale of Glamorgan | 10.0 |
Smaller schemes under 1 MW, mostly rooftop solar (21)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| The Maltings East, Tyndall Streetsolar farm | solar farm | 0.6 | approved, not builtupdated Jan 2024 | Aug 2023 | granted Nov 2023 | Jan 2024 | Cardiff | 1.2 |
| Cardiff Universityrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Sep 2024 | Jun 2024 | granted Aug 2024 | Sep 2024 | Cardiff | 1.4 |
| Ocean Park Arena, Splott Solar Arraysrooftop solar | rooftop solar | 0.4 | approved, not builtupdated Mar 2026 | Dec 2025 | granted Jan 2026 | Mar 2026 | Cardiff | 1.4 |
| Portmanmoor Road Industrial Estate, Portmanmoor Roadrooftop solar | rooftop solar | 0.4 | approved, not builtupdated Jun 2023 | Mar 2023 | granted Jun 2023 | Jun 2023 | Cardiff | 1.6 |
| David Lloyd Leisure Club, Ipswich Roadrooftop solar | rooftop solar | 0.4 | approved, not builtupdated Mar 2024 | Feb 2024 | granted Feb 2024 | Mar 2024 | Cardiff | 1.7 |
| Tramshed, Pendyris Street Solar Panels & Battery Storagerooftop solar | rooftop solar | — | application submitted may be out of dateupdated Dec 2022 | Nov 2022 | — | Dec 2022 | Cardiff | 2.2 |
| Tramshed, Pendyris Street Solar Panels & Battery Storagebattery storage | battery storage | — | application submitted may be out of dateupdated Dec 2022 | Nov 2022 | — | Dec 2022 | Cardiff | 2.2 |
| Llanedeyrn Drive - Micro Energy Storage Projectbattery storage | battery storage | 0.2 | approved, not builtupdated Jun 2026 | Jan 2026 | granted May 2026 | Jun 2026 | Cardiff | 2.3 |
| The Wales Millennium Centre, Bute Placebattery storage | battery storage | 0.5 | approved, not builtupdated Jun 2026 | Mar 2026 | granted Apr 2026 | Jun 2026 | Cardiff | 2.6 |
| University Hospital of Walesrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Jun 2022 | Jun 2022 | granted Jun 2022 | Jun 2022 | Cardiff | 2.7 |
| Techniquest, Stuart Streetrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Aug 2023 | Jun 2023 | granted Jul 2023 | Aug 2023 | Cardiff | 2.9 |
| Gabalfa Interchange - Micro Energy Storagebattery storage | battery storage | 0.2 | approved, not builtupdated Jul 2026 | Jan 2026 | granted May 2026 | Jul 2026 | Cardiff | 3.2 |
| Brynwell Farmbattery storage | battery storage | — | approved, not builtupdated Feb 2026 | Apr 2021 | granted Nov 2022 | Feb 2026 | Vale of Glamorgan | 4.8 |
| Spire Cardiff Hospital, Croescadarn Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Sep 2024 | May 2024 | granted Jul 2024 | Sep 2024 | Cardiff | 5.0 |
| University Hospital, Penlan Road Solar Arraysrooftop solar | rooftop solar | 0.7 | approved, not builtupdated Nov 2022 | Sep 2022 | granted Oct 2022 | Nov 2022 | Vale of Glamorgan | 5.2 |
| Llandough Hospital, Llandoughrooftop solar | rooftop solar | 0.7 | approved, not built may be out of dateupdated Mar 2024 | Nov 2023 | granted Feb 2024 | Mar 2024 | Vale of Glamorgan | 5.2 |
| Llanishen High Schoolrooftop solar | rooftop solar | 0.2 | approved, not built may be out of dateupdated Mar 2019 | Feb 2019 | granted Mar 2019 | Mar 2019 | Cardiff | 5.2 |
| Began Road - Ground Mounted Solar Pv arraysolar farm | solar farm | 0.2 | application withdrawnupdated Mar 2022 | Feb 2022 | — | Mar 2022 | Newport | 7.2 |
| Caerau Lane, By Port Lane - Micro Energy Storagebattery storage | battery storage | 0.2 | application submitted | Apr 2026 | — | — | Vale of Glamorgan | 8.4 |
| Vianshill Farm, Parc Dyffryn Solar Farm & Battery Storagebattery storage | battery storage | — | approved, not builtupdated Feb 2026 | Oct 2022 | granted May 2024 | Feb 2026 | Vale of Glamorgan | 9.1 |
| Wentlooge Renewable Energy Hubbattery storage | battery storage | — | appeal lodged may be out of dateupdated Feb 2024 | Jun 2022 | — | Feb 2024 | Newport | 9.4 |
Distance from the average position of the CF24 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 12 | 1 | 4 | 6 | 0 | 213 |
| Rooftop solar | 14 | 1 | 11 | 2 | 0 | 4.7 |
| Solar | 1 | 0 | 0 | 0 | 0 | 0 |
| Wind turbine | 1 | 0 | 0 | 1 | 0 | 0 |
| Battery storage | 13 | 3 | 9 | 0 | 1 | 1,145 |
MW in pipeline: pending, approved and under-construction capacity.
How Cardiff decides solar, wind and battery applications
| Applications | Cardiff | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 19 | 10,236 |
| Refused | 0 (0%) | 19% |
| Solar refused | 0 of 12 | 12% |
| Onshore wind refused | 0 of 1 | 45% |
| Battery storage refused | 0 of 6 | 16% |
| Median time from submission to decision | 9.1 weeks | 17.0 weeks |
| Appeals lodged / allowed | 0 / 0 | — |
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near CF24, 6 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.