Energy Projects Near You

Lamby Way Solar Farm (8.9 MW)

Lamby Way Solar Farm is an 8.9 MW solar farm project in Cardiff, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 May 2020; the record was last updated on 12 January 2021.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

8.9 MWsolar farm
operationalstatus in REPD
12 January 2021record last updated
Cardiffcouncil area

Planning timeline

DateStage
22 February 2019Application submitted
10 May 2019Planning permission granted
26 November 2019Construction started
1 May 2020Operational

Project details

Technology
solar farm
Capacity
8.9 MW
Status (REPD)
operational
Record last updated
12 January 2021
Operator or applicant
Cardiff Council
Planning authority
Cardiff
Planning application reference
19/00397/MJR
Site area
16.9 ha
Address (REPD)
Former Lamby Way landfill site, Lamby Way, Rumney, Cardiff, South Glamorgan
Council area (by location)
Cardiff
Time to decision
11 weeks
REPD reference
6660

Who decides

ApplicationsCardiffUK
Decided applications (solar, wind, battery)1910,236
Refused0 (0%)19%
Solar refused0 of 1212%
Onshore wind refused0 of 145%
Battery storage refused0 of 616%
Median time from submission to decision9.1 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Rover Way, Splott Energy Park & Data Centrebattery storage1,000approved, not built1.1
Ipswich Road, Cardiffbattery storage93approved, not built1.4
Coal Pit Lanesolar5.3application withdrawn5.9
Wentlooge Renewable Energy Hubsolar farm125appeal lodged7.0
Brynwell Farmsolar farm21approved, not built7.9
Woden Parksolar farm5operational8.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.4942, -3.126).