Brynwell Farm (21 MW solar farm)

Brynwell Farm is a 21 MW solar farm project in Cardiff, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 10 November 2022, not yet built; the record was last updated on 16 February 2026. It is decided by the Welsh Government as a development of national significance.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

21 MWsolar farm
approved, not builtstatus in REPD
16 February 2026record last updated
Cardiffcouncil area

Planning timeline

DateStage
21 April 2021Application submitted
10 November 2022Planning permission granted
10 November 2027Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
21 MW
Status (REPD)
approved, not built
Record last updated
16 February 2026
Operator or applicant
Brynwell Farm Solar Limited
Planning authority
Welsh Government (NSIP)
Planning application reference
DNS/3261558
Address (REPD)
Brynwell Farm, on land between the A4232 and Leckwith village
Council area (by location)
Cardiff
Time to decision
81 weeks
Contracts for Difference
AR7a
REPD reference
8088

The scheme also includes battery storage, recorded separately in REPD (approved, not built).

Who decides

It is decided by the Welsh Government as a development of national significance. Welsh Government (NSIP) refused 22% of 55 decided solar, wind and battery applications in REPD (median 67 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Woden Parksolar farm5operational0.9
Vianshill Farm, Parc Dyffryn Solar Farm & Battery Storagesolar farm65approved, not built3.8
Biglis Farmsolar farm5operational4.7
Parc Worlton Solar Farmsolar farm42approved, not built5.7
Sully Moors Roadbattery storage50approved, not built5.8
Pen Y Maes, Ashby Roadbattery storage50refused6.0
Whitton Mawrsolar farm6operational7.0
Ipswich Road, Cardiffbattery storage93approved, not built7.0
Castle Road, Burtonbattery storage440application submitted7.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.4649, -3.2307).