Parc Worlton Solar Farm (42 MW)

Parc Worlton Solar Farm is a 42 MW solar farm project in Vale of Glamorgan, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 21 January 2025, not yet built; the record was last updated on 23 February 2026. It is decided by the Welsh Government as a development of national significance.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

42 MWsolar farm
approved, not builtstatus in REPD
23 February 2026record last updated
Vale of Glamorgancouncil area

Planning timeline

DateStage
24 November 2023Application submitted
21 January 2025Planning permission granted
21 January 2030Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
42 MW
Status (REPD)
approved, not built
Record last updated
23 February 2026
Operator or applicant
Lightrock Power
Planning authority
Welsh Government (NSIP)
Planning application reference
CAS-02112-T2N0G8
Site area
49.1 ha
Address (REPD)
S/O St Lythans Road, Cardiff
Council area (by location)
Vale of Glamorgan
Time to decision
61 weeks
Contracts for Difference
AR7a
REPD reference
12020

Who decides

It is decided by the Welsh Government as a development of national significance. Welsh Government (NSIP) refused 22% of 55 decided solar, wind and battery applications in REPD (median 67 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Whitton Mawrsolar farm6operational1.4
Weycock Roadsolar farm7operational2.5
Cwm Derwyn Farmsolar farm5operational2.8
Vianshill Farm, Parc Dyffryn Solar Farm & Battery Storagesolar farm65approved, not built2.8
Sutton Mawr Solar Farm (extension)solar farm8abandoned2.8
Sutton Mawr Farmsolar farm7.5operational2.9
Pancross & Oaklands Solar Farmsolar farm50under construction3.7
Castle Road, Burtonbattery storage440application submitted4.5
Land at Pen Onn Solar Farmsolar farm45approved, not built4.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.4401, -3.3033).