Sutton Mawr Farm (7.5 MW solar farm)

Sutton Mawr Farm is a 7.5 MW solar farm project in Vale of Glamorgan, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 4 March 2014; the record was last updated on 29 October 2014.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

7.5 MWsolar farm
operationalstatus in REPD
29 October 2014record last updated
Vale of Glamorgancouncil area

Planning timeline

DateStage
2 July 2013Application submitted
17 January 2014Planning permission granted
4 March 2014Operational

Project details

Technology
solar farm
Capacity
7.5 MW
Status (REPD)
operational
Record last updated
29 October 2014
Operator or applicant
Lightsource Renewable Energy
Planning authority
Vale of Glamorgan
Planning application reference
2013/00617/FUL
Site area
19.1 ha
Address (REPD)
Sutton Mawr Farm, Barry, South Glamorgan
Council area (by location)
Vale of Glamorgan
Time to decision
28 weeks
REPD reference
1823

Who decides

ApplicationsVale of GlamorganUK
Decided applications (solar, wind, battery)3010,236
Refused4 (13%)19%
Solar refused3 of 2712%
Battery storage refused1 of 316%
Median time from submission to decision19.9 weeks17.0 weeks
Appeals lodged / allowed0 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Sutton Mawr Solar Farm (extension)solar farm8abandoned0.1
Cwm Derwyn Farmsolar farm5operational0.9
Weycock Roadsolar farm7operational1.4
Whitton Mawrsolar farm6operational2.5
Land at Pen Onn Solar Farmsolar farm45approved, not built2.5
Parc Worlton Solar Farmsolar farm42approved, not built2.9
East Aberthaw Solar farmsolar farm35approved, not built3.4
Castle Road, Burtonbattery storage440application submitted3.9
Pancross & Oaklands Solar Farmsolar farm50under construction4.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.4186, -3.327).