Pancross & Oaklands Solar Farm (50 MW)

Pancross & Oaklands Solar Farm is a 50 MW solar farm project in Vale of Glamorgan, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: under construction since 1 October 2025; the record was last updated on 19 February 2026. It is decided by the Welsh Government as a development of national significance.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

50 MWsolar farm
under constructionstatus in REPD
19 February 2026record last updated
Vale of Glamorgancouncil area

Planning timeline

DateStage
4 May 2023Application submitted
23 May 2024Planning permission granted
1 October 2025Construction started

Project details

Technology
solar farm
Capacity
50 MW
Status (REPD)
under construction
Record last updated
19 February 2026
Operator or applicant
Infinis
Planning authority
Welsh Government (NSIP)
Planning application reference
DNS/3245503
Address (REPD)
Land at Pancross and Oaklands Farm, near Bonvilston,
Council area (by location)
Vale of Glamorgan
Time to decision
55 weeks
Contracts for Difference
AR7a
REPD reference
7701

The scheme also includes 50 MW of battery storage, recorded separately in REPD (under construction).

Who decides

It is decided by the Welsh Government as a development of national significance. Welsh Government (NSIP) refused 22% of 55 decided solar, wind and battery applications in REPD (median 67 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Whitton Mawrsolar farm6operational2.4
Garn Solar Farmsolar farm7.4operational2.4
Land at Pen Onn Solar Farmsolar farm45approved, not built3.7
Parc Worlton Solar Farmsolar farm42approved, not built3.7
Sutton Mawr Solar Farm (extension)solar farm8abandoned4.1
Sutton Mawr Farmsolar farm7.5operational4.2
Lane South-East from Cowbridgesolar farm5refused4.2
Vianshill Farm, Parc Dyffryn Solar Farm & Battery Storagesolar farm65approved, not built4.8
Cwm Derwyn Farmsolar farm5operational4.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.4522, -3.3534).