Lane South-East from Cowbridge (5 MW solar farm)

Lane South-East from Cowbridge is a 5 MW solar farm project in Vale of Glamorgan, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 20 November 2015; the record was last updated on 2 December 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
refusedstatus in REPD
2 December 2015record last updated
Vale of Glamorgancouncil area

Planning timeline

DateStage
29 June 2015Application submitted
20 November 2015Refused by the planning authority

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
refused
Record last updated
2 December 2015
Operator or applicant
Solar Century
Planning authority
Vale of Glamorgan
Planning application reference
2015/00649/FUL
Address (REPD)
The Farm, , St. Hilary, The Farm, lane South-East from, Cowbridge, South Glamorgan
Council area (by location)
Vale of Glamorgan
Time to decision
21 weeks
REPD reference
5436

Who decides

ApplicationsVale of GlamorganUK
Decided applications (solar, wind, battery)3010,236
Refused4 (13%)19%
Solar refused3 of 2712%
Battery storage refused1 of 316%
Median time from submission to decision19.9 weeks17.0 weeks
Appeals lodged / allowed0 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Garn Solar Farmsolar farm7.4operational1.8
Pancross & Oaklands Solar Farmsolar farm50under construction4.2
Aston Martin Lagonda, Llanmaesrooftop solar6approved, not built4.6
Land at Pen Onn Solar Farmsolar farm45approved, not built4.9
Llancadle Farmsolar farm5operational5.2
West Hall Solar Farmsolar farm7operational6.2
Aberthaw Battery Energy Storage Systembattery storage249application submitted6.3
Whitton Mawrsolar farm6operational6.3
East Aberthaw Solar farmsolar farm35approved, not built6.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.45, -3.4143).