Aston Martin Lagonda, Llanmaes (6 MW rooftop solar)
Aston Martin Lagonda, Llanmaes is a 6 MW rooftop solar project in Vale of Glamorgan, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 6 February 2024, not yet built; the record was last updated on 27 February 2024.
6 MWrooftop solar
approved, not builtstatus in REPD
27 February 2024record last updated
Vale of Glamorgancouncil area
Planning timeline
| Date | Stage |
|---|---|
| 17 August 2023 | Application submitted |
| 6 February 2024 | Planning permission granted |
| 6 February 2029 | Permission due to expire (unless work starts) |
Project details
- Technology
- rooftop solar
- Capacity
- 6 MW
- Status (REPD)
- approved, not built
- Record last updated
- 27 February 2024
- Operator or applicant
- Aston Martin Lagonda
- Planning authority
- Vale of Glamorgan
- Planning application reference
- 2023/00617/FUL
- Address (REPD)
- Aston Martin Lagonda, Llanmaes, Barry
- Council area (by location)
- Vale of Glamorgan
- Time to decision
- 25 weeks
- Name in REPD
- Aston Martin Lagonda, Llanmaes - Solar Pv Panels
- REPD reference
- 14735
Who decides
| Applications | Vale of Glamorgan | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 30 | 10,236 |
| Refused | 4 (13%) | 19% |
| Solar refused | 3 of 27 | 12% |
| Battery storage refused | 1 of 3 | 16% |
| Median time from submission to decision | 19.9 weeks | 17.0 weeks |
| Appeals lodged / allowed | 0 / 1 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Aberthaw Battery Energy Storage System | battery storage | 249 | application submitted | 2.4 |
| West Hall Solar Farm | solar farm | 7 | operational | 2.7 |
| Rosedew Farm | solar farm | 5 | operational | 3.0 |
| Llancadle Farm | solar farm | 5 | operational | 3.3 |
| Lane South-East from Cowbridge | solar farm | 5 | refused | 4.6 |
| Land at Pen Onn Solar Farm | solar farm | 45 | approved, not built | 4.9 |
| East Aberthaw Solar farm | solar farm | 35 | approved, not built | 5.1 |
| Garn Solar Farm | solar farm | 7.4 | operational | 5.7 |
| Pancross & Oaklands Solar Farm | solar farm | 50 | under construction | 7.2 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.4107, -3.4336).