Energy Projects Near You

Rosedew Farm (5 MW solar farm)

Rosedew Farm is a 5 MW solar farm project in Vale of Glamorgan, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 29 March 2016; the record was last updated on 4 April 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
4 April 2017record last updated
Vale of Glamorgancouncil area

Planning timeline

DateStage
2 March 2015Application submitted
29 January 2016Construction started
29 March 2016Operational
4 November 2022Planning permission granted

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
4 April 2017
Operator or applicant
INRG
Planning authority
Vale of Glamorgan
Planning application reference
2015/00218/FUL
Site area
10.7 ha
Address (REPD)
Land at Rosedew Farm, Beach Road, Llantwit Major
Council area (by location)
Vale of Glamorgan
Time to decision
401 weeks
REPD reference
6369

Who decides

ApplicationsVale of GlamorganUK
Decided applications (solar, wind, battery)3010,236
Refused4 (13%)19%
Solar refused3 of 2712%
Battery storage refused1 of 316%
Median time from submission to decision19.9 weeks17.0 weeks
Appeals lodged / allowed0 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Aston Martin Lagonda, Llanmaesrooftop solar6approved, not built3.0
Aberthaw Battery Energy Storage Systembattery storage249application submitted4.1
West Hall Solar Farmsolar farm7operational4.6
Llancadle Farmsolar farm5operational5.9
Lane South-East from Cowbridgesolar farm5refused7.0
East Aberthaw Solar farmsolar farm35approved, not built7.5
Land at Pen Onn Solar Farmsolar farm45approved, not built7.8
Garn Solar Farmsolar farm7.4operational8.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.3976, -3.4707).