Energy Projects Near You

Aberthaw Battery Energy Storage System (249 MW)

Aberthaw Battery Energy Storage System is a 249 MW battery storage project in Vale of Glamorgan, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application submitted on 16 December 2025, no decision recorded; the record was last updated on 9 March 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

249 MWbattery storage
application submittedstatus in REPD
9 March 2026record last updated
Vale of Glamorgancouncil area

Planning timeline

DateStage
16 December 2025Application submitted

Project details

Technology
battery storage (stand-alone storage)
Capacity
249 MW
Status (REPD)
application submitted
Record last updated
9 March 2026
Operator or applicant
Aberthaw Energy Limited
Planning authority
Vale of Glamorgan
Planning application reference
2025/01282/FUL
Address (REPD)
Gileston Farm, Gileston
Council area (by location)
Vale of Glamorgan
REPD reference
20451

Who decides

ApplicationsVale of GlamorganUK
Decided applications (solar, wind, battery)3010,236
Refused4 (13%)19%
Solar refused3 of 2712%
Battery storage refused1 of 316%
Median time from submission to decision19.9 weeks17.0 weeks
Appeals lodged / allowed0 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
West Hall Solar Farmsolar farm7operational0.5
Llancadle Farmsolar farm5operational2.3
Aston Martin Lagonda, Llanmaesrooftop solar6approved, not built2.4
East Aberthaw Solar farmsolar farm35approved, not built3.4
Rosedew Farmsolar farm5operational4.1
Land at Pen Onn Solar Farmsolar farm45approved, not built4.4
Lane South-East from Cowbridgesolar farm5refused6.3
Sutton Mawr Farmsolar farm7.5operational6.5
Sutton Mawr Solar Farm (extension)solar farm8abandoned6.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.3936, -3.4118).