Energy Projects Near You

West Hall Solar Farm (7 MW)

West Hall Solar Farm is a 7 MW solar farm project in Vale of Glamorgan, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 31 March 2014; the record was last updated on 10 May 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

7 MWsolar farm
operationalstatus in REPD
10 May 2016record last updated
Vale of Glamorgancouncil area

Planning timeline

DateStage
1 August 2013Application submitted
17 January 2014Planning permission granted
18 January 2014Construction started
31 March 2014Operational

Project details

Technology
solar farm
Capacity
7 MW
Status (REPD)
operational
Record last updated
10 May 2016
Operator or applicant
INRG Solar
Planning authority
Vale of Glamorgan
Planning application reference
2013/00724/FUL
Site area
16.3 ha
Address (REPD)
Land at West Hall Farm, Aberthaw, St. Athan
Council area (by location)
Vale of Glamorgan
Time to decision
24 weeks
REPD reference
2359

Who decides

ApplicationsVale of GlamorganUK
Decided applications (solar, wind, battery)3010,236
Refused4 (13%)19%
Solar refused3 of 2712%
Battery storage refused1 of 316%
Median time from submission to decision19.9 weeks17.0 weeks
Appeals lodged / allowed0 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Aberthaw Battery Energy Storage Systembattery storage249application submitted0.5
Llancadle Farmsolar farm5operational1.8
Aston Martin Lagonda, Llanmaesrooftop solar6approved, not built2.7
East Aberthaw Solar farmsolar farm35approved, not built2.9
Land at Pen Onn Solar Farmsolar farm45approved, not built4.0
Rosedew Farmsolar farm5operational4.6
Sutton Mawr Farmsolar farm7.5operational6.0
Sutton Mawr Solar Farm (extension)solar farm8abandoned6.1
Lane South-East from Cowbridgesolar farm5refused6.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.3949, -3.4049).