Weycock Road (7 MW solar farm)

Weycock Road is a 7 MW solar farm project in Vale of Glamorgan, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 2 March 2016; the record was last updated on 21 June 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

7 MWsolar farm
operationalstatus in REPD
21 June 2016record last updated
Vale of Glamorgancouncil area

Planning timeline

DateStage
22 January 2014Application submitted
1 August 2014Planning permission granted
26 November 2015Construction started
2 March 2016Operational

Project details

Technology
solar farm
Capacity
7 MW
Status (REPD)
operational
Record last updated
21 June 2016
Operator or applicant
Elgin Energy EsCo
Planning authority
Vale of Glamorgan
Planning application reference
2014/00081/FUL
Site area
17.9 ha
Address (REPD)
Land off Weycock Cross, Waycock Road, Barry, South Glamorgan
Council area (by location)
Vale of Glamorgan
Time to decision
27 weeks
REPD reference
2338

Who decides

ApplicationsVale of GlamorganUK
Decided applications (solar, wind, battery)3010,236
Refused4 (13%)19%
Solar refused3 of 2712%
Battery storage refused1 of 316%
Median time from submission to decision19.9 weeks17.0 weeks
Appeals lodged / allowed0 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Cwm Derwyn Farmsolar farm5operational0.5
Sutton Mawr Solar Farm (extension)solar farm8abandoned1.3
Sutton Mawr Farmsolar farm7.5operational1.4
Parc Worlton Solar Farmsolar farm42approved, not built2.5
Castle Road, Burtonbattery storage440application submitted2.7
Whitton Mawrsolar farm6operational2.9
Land at Pen Onn Solar Farmsolar farm45approved, not built3.9
Port of Barry - Site 2solar farm5operational4.4
East Aberthaw Solar farmsolar farm35approved, not built4.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.4178, -3.3075).