Energy Projects Near You

Solar, wind and battery projects near London (EC4Y)

66 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of EC4Y (City of London): 10 are waiting for a planning decision, 43 approved but not yet running, 3 operational. The largest live scheme is Solar Panels at Hedgehog Grove Solar Farm (98 MW solar farm, application submitted on 24 March 2026, no decision recorded), 6.4 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

66projects within 10 km
10awaiting a decision
43approved, not running
3operational

Projects within 10 km of EC4Y

Projects of 1 MW and more (8)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Pegasus House, Sackville Streetrooftop solarrooftop solar2.3approved, not built may be out of dateupdated Dec 2021Nov 2021granted Dec 2021Dec 2021Westminster2.1
Solar Panels at Hedgehog Grove Solar Farmsolar farmsolar farm98application submittedupdated Apr 2026Mar 2026—Apr 2026Tower Hamlets6.4
Olympic Park Wind Turbinewind turbinewind turbine2.5abandonedupdated Oct 2010Jan 2007granted Sep 2007Oct 2010Newham7.1
Bywaters’ Materials Recovery Facility Solar Arrayrooftop solarrooftop solar1operationalupdated Feb 2017Oct 2015granted Dec 2015Feb 2017Tower Hamlets7.1
Westfield London Shopping Centre, Ariel Wayrooftop solarrooftop solar1application submitted may be out of dateupdated Jul 2023Jun 2023—Jul 2023Hammersmith and Fulham7.8
The O2 Arenawind farmwind farm3approved, not built may be out of dateupdated Oct 2021Jun 2021granted Sep 2021Oct 2021Greenwich8.0
Alcatel, Telegraph Houserooftop solarrooftop solar1.3refusedupdated Dec 2025Sep 2025refused Oct 2025Dec 2025Greenwich8.4
Thameside DCrooftop solarrooftop solar1operationalupdated Feb 2016——Feb 2016Greenwich9.7
Smaller schemes under 1 MW, mostly rooftop solar (58)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Bush Houserooftop solarrooftop solar—approved, not built may be out of dateupdated Jun 2021Apr 2021granted May 2021Jun 2021Westminster0.6
Lindsey Streetrooftop solarrooftop solar0.2approved, not builtupdated Dec 2025Oct 2025granted Nov 2025Dec 2025City of London1.0
Cannon Streetrooftop solarrooftop solar0.3approved, not builtupdated Jan 2025Sep 2024granted Dec 2024Jan 2025City of London1.3
Tower Place Westrooftop solarrooftop solar0.4approved, not builtupdated Mar 2025Jan 2025granted Feb 2025Mar 2025City of London2.0
University College Hospital, Euston Roadrooftop solarrooftop solar0.2approved, not built may be out of dateupdated Nov 2022Sep 2022granted Nov 2022Nov 2022Camden2.3
London St Pancras International Station - Installation Of Solar Panelsrooftop solarrooftop solar—no application requiredupdated Mar 2025——Mar 2025Camden2.4
Jobcentreplus, Drysdale Streetrooftop solarrooftop solar—approved, not builtupdated Sep 2025May 2025granted Jul 2025Sep 2025Hackney2.6
Consession Queen Mother Sports Centrerooftop solarrooftop solar—application submitted may be out of dateupdated Oct 2021Oct 2021—Oct 2021Westminster3.1
The Highway - 114 Flats, Office Accomodation & Self Storage Facilityrooftop solarrooftop solar0.2approved, not builtupdated Jul 2024Dec 2021granted Aug 2023Jul 2024Tower Hamlets3.3
John Orwell Sports Centre, Tench Streetrooftop solarrooftop solar0.3approved, not builtupdated May 2025Feb 2025granted Apr 2025May 2025Tower Hamlets3.4
Dolphin Squarerooftop solarrooftop solar—under constructionupdated May 2022Apr 2022granted Dec 2022May 2022Westminster3.5
Walworth Academy, Shorncliffe Roadrooftop solarrooftop solar0.3approved, not builtupdated Feb 2024Dec 2023granted Jan 2024Feb 2024Southwark3.5
The Bermondsey Projectrooftop solarrooftop solar0.2approved, not builtupdated Oct 2023Oct 2017granted Jun 2020Oct 2023Southwark3.8
City Of London Academyrooftop solarrooftop solar0.2approved, not built may be out of dateupdated May 2022Feb 2022granted May 2022May 2022Southwark4.0
London Zoo, Outer Circlerooftop solarrooftop solar0.2approved, not builtupdated May 2025Feb 2025granted Apr 2025May 2025Westminster4.1
Waste & Recycling centre, Hornsey Streetrooftop solarrooftop solar0.4approved, not builtupdated Nov 2023Sep 2023granted Nov 2023Nov 2023Islington4.1
Holly Streetrooftop solarrooftop solar0.2operationalupdated Jan 2022Aug 2021granted Feb 2023Jan 2022Hackney4.2
Town Hall Hotel, Patriot Squarerooftop solarrooftop solar0.1application submittedMay 2026——Tower Hamlets4.2
Mowlem Junior And Infant School, Mowlem Streetrooftop solarrooftop solar0.2approved, not builtupdated Jun 2026Mar 2026granted May 2026Jun 2026Tower Hamlets4.4
Imperial College Health CentreSolar Panelsrooftop solarrooftop solar—application withdrawnupdated Apr 2021Feb 2021—Apr 2021Westminster4.7
Crompton Streetrooftop solarrooftop solar0.2approved, not builtupdated Dec 2021Oct 2021granted Nov 2021Dec 2021Westminster4.8
Peckham Pulse Leisure Centre, Melon Roadrooftop solarrooftop solar0.2approved, not builtupdated Feb 2025Nov 2024granted Jan 2025Feb 2025Southwark5.1
Battersea Studiosrooftop solarrooftop solar0.4approved, not builtupdated Sep 2024Jul 2024granted Sep 2024Sep 2024Wandsworth5.2
William Booth Training College, Champion Parkrooftop solarrooftop solar—approved, not built may be out of dateupdated Jul 2023Feb 2023granted Aug 2023Jul 2023Southwark5.3
William Booth Training College, Champion Parkrooftop solarrooftop solar—application submitted may be out of dateupdated Jul 2023Jul 2023—Jul 2023Southwark5.3
Chelsea And Westminster Hospital, Fulham Road - Photovoltaic Panelsrooftop solarrooftop solar0.2approved, not builtupdated Jun 2026Mar 2026granted Apr 2026Jun 2026Kensington and Chelsea6.0
Homerton University Hospital, Homerton Groverooftop solarrooftop solar0.3approved, not builtupdated Apr 2026Jan 2026granted Feb 2026Apr 2026Hackney6.0
David Lloyd Leisurerooftop solarrooftop solar0.2refusedupdated Sep 2025Jul 2025refused Sep 2025Sep 2025Westminster6.1
Citibank, 25 Canada Square - Office Fit-Out & Refurbishmentrooftop solarrooftop solar—no application requiredupdated Feb 2022——Feb 2022Tower Hamlets6.4
45 Clapham Campus South Side - 525 Flats & Education Facilityrooftop solarrooftop solar0.2application submitted may be out of dateupdated Apr 2023Oct 2022—Apr 2023Lambeth6.4
Henderson Court, Fitzjohns Avenuerooftop solarrooftop solar0.2approved, not built may be out of dateupdated Nov 2022Aug 2022granted Nov 2022Nov 2022Camden6.6
Harbour club, Watermeadow Lanerooftop solarrooftop solar0.4application withdrawnupdated Jul 2024Nov 2023—Jul 2024Hammersmith and Fulham7.1
Kensington Leisure Centre, Silchester Roadrooftop solarrooftop solar0.2approved, not built may be out of dateupdated Mar 2023Oct 2022granted Feb 2023Mar 2023Kensington and Chelsea7.4
Fulham Pools, Lillie Roadrooftop solarrooftop solar0.3approved, not builtupdated May 2024Jan 2024granted Apr 2024May 2024Hammersmith and Fulham7.6
Segro Park Canning, Town Bidder Street, Unit 2rooftop solarrooftop solar0.2approved, not builtupdated Aug 2025Jun 2025granted Jul 2025Aug 2025Newham7.6
Moberly Sports Centre - Photovoltaic Arraysrooftop solarrooftop solar0.2approved, not builtupdated Nov 2021Nov 2021granted Dec 2021Nov 2021Brent7.7
Moberly Sports Centre - Photovoltaic Arraysrooftop solarrooftop solar—refusedupdated Oct 2021Oct 2021refused Oct 2021Oct 2021Brent7.7
The Queens Club, Palliser Roadrooftop solarrooftop solar0.5approved, not built may be out of dateupdated Jun 2023Feb 2023granted May 2023Jun 2023Hammersmith and Fulham7.7
Westfield Stratford City, Montfichet Roadrooftop solarrooftop solar0.3approved, not builtupdated Aug 2023Jun 2023granted Aug 2023Aug 2023Newham7.8
Westfield London Shopping Centre, Ariel Wayrooftop solarrooftop solar0.3application submittedupdated Feb 2026Jan 2026—Feb 2026Hammersmith and Fulham7.9
New Spitalfields Market, Allen Houserooftop solarrooftop solar0.2approved, not builtupdated Jun 2026Feb 2026granted Apr 2026Jun 2026Waltham Forest7.9
Paul Rhodes Bakery Limited, Lassell Streetrooftop solarrooftop solar—refusedupdated May 2025Mar 2025refused May 2025May 2025Greenwich8.2
Dulwich College, College Roadrooftop solarrooftop solar0.7approved, not builtupdated Feb 2025Jun 2024granted Dec 2024Feb 2025Southwark8.4
Coppermill Workssolar farmsolar farm0.7application submitted may be out of dateupdated Aug 2022Jul 2022—Aug 2022Waltham Forest8.6
Kern House, Scrubs Lanerooftop solarrooftop solar—approved, not builtupdated Sep 2023Aug 2023granted Sep 2023Sep 2023Hammersmith and Fulham8.7
Hammersmith Hospital, Du Cane Roadrooftop solarrooftop solar0.2approved, not builtupdated Aug 2025Mar 2025granted Jul 2025Aug 2025Hammersmith and Fulham8.7
Phoenix Fitness Centre, Phoenix Closerooftop solarrooftop solar0.2approved, not builtupdated Apr 2024Jan 2024granted Mar 2024Apr 2024Hammersmith and Fulham8.8
University Of East London - 650 Student accommodation & Teaching and learningrooftop solarrooftop solar0.2under constructionupdated Jun 2026Apr 2023granted Aug 2025Jun 2026Newham8.9
Millennium Retail Park - Flats & Retail Spacerooftop solarrooftop solar0.3application submitted may be out of dateupdated Sep 2024May 2024—Sep 2024Greenwich8.9
Willesden Sports Centre, Donnington Roadrooftop solarrooftop solar0.3approved, not builtupdated Apr 2025Jan 2025granted Mar 2025Apr 2025Brent9.0
University Of East London, Stratford Cam PV Panelsrooftop solarrooftop solar0.2approved, not builtupdated Apr 2024Jan 2024granted Mar 2024Apr 2024Newham9.0
Wood Green Shopping City, High Roadrooftop solarrooftop solar0.3approved, not builtupdated May 2026Jan 2026granted Mar 2026May 2026Haringey9.1
Custom Housebattery storagebattery storage0.2approved, not builtupdated Sep 2025Feb 2025granted Aug 2025Sep 2025Newham9.2
Springfield University Hospitalrooftop solarrooftop solar—approved, not builtupdated Jun 2026Nov 2025granted May 2026Jun 2026Wandsworth9.4
Knights Hill Solar PV equipmentrooftop solarrooftop solar0.2approved, not builtupdated Sep 2023Aug 2023granted Sep 2023Sep 2023Lambeth9.6
Springfield University Hospital, Lapidge Driverooftop solarrooftop solar—refusedupdated Apr 2026Dec 2025refused Feb 2026Apr 2026Wandsworth9.6
Newham Leisure Centre, Prince Regent Lanerooftop solarrooftop solar0.2application submitted may be out of dateupdated Feb 2023Dec 2022—Feb 2023Newham9.8
Streatham Ice & Leisure, Streatham High Road Solar Panels & ASHProoftop solarrooftop solar0.3approved, not builtupdated Mar 2024Nov 2023granted Mar 2024Mar 2024Lambeth10.0

Distance from the average position of the EC4Y postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm2200098.7
Rooftop solar618413513.5
Wind farm101003
Wind turbine100000
Battery storage101000.2

MW in pipeline: pending, approved and under-construction capacity.

How City of London decides solar, wind and battery applications

City of London has 4 decided solar, wind or battery applications in REPD — too few for a refusal rate (we show one from 10 decisions). Across all UK planning authorities 19% of 10,236 decisions were refusals.

All projects in City of London

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near EC4Y, 16 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.