Energy Projects Near You

Solar, wind and battery projects near Lynton (EX35)

1 solar, wind or battery project of 150 kW or more is recorded within 10 km of the centre of EX35 (North Devon): 1 approved but not yet running. The largest live scheme is The Hayloft ( MW rooftop solar, approved on 21 April 2021, not yet built; REPD status may be out of date), 1.0 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

1projects within 10 km
0awaiting a decision
1approved, not running
0operational

Projects within 10 km of EX35

Smaller schemes under 1 MW, mostly rooftop solar (1)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
The Hayloftrooftop solarrooftop solar—approved, not built may be out of dateupdated Jun 2021Jan 2021granted Apr 2021Jun 2021North Devon1.0

Distance from the average position of the EX35 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Rooftop solar101000

MW in pipeline: pending, approved and under-construction capacity.

How North Devon decides solar, wind and battery applications

ApplicationsNorth DevonUK
Decided applications (solar, wind, battery)3710,236
Refused9 (24%)19%
Solar refused4 of 2612%
Onshore wind refused5 of 645%
Battery storage refused0 of 516%
Median time from submission to decision23.3 weeks17.0 weeks
Appeals lodged / allowed1 / 3—

All projects in North Devon

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near EX35, 1 project has a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.