Energy Projects Near You

Solar, wind and battery projects near Callander (FK17)

1 solar, wind or battery project of 150 kW or more is recorded within 10 km of the centre of FK17 (Stirling): 1 approved but not yet running. The largest live scheme is McLaren Leisure Centre (0.2 MW rooftop solar, approved on 2 February 2026, not yet built), 0.6 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

1projects within 10 km
0awaiting a decision
1approved, not running
0operational

Projects within 10 km of FK17

Smaller schemes under 1 MW, mostly rooftop solar (1)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
McLaren Leisure Centrerooftop solarrooftop solar0.2approved, not builtupdated Mar 2026Dec 2025granted Feb 2026Mar 2026Stirling0.6

Distance from the average position of the FK17 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Rooftop solar101000.2

MW in pipeline: pending, approved and under-construction capacity.

How Stirling decides solar, wind and battery applications

ApplicationsStirlingUK
Decided applications (solar, wind, battery)2310,236
Refused7 (30%)19%
Solar refused0 of 712%
Onshore wind refused6 of 1145%
Battery storage refused1 of 516%
Median time from submission to decision30.1 weeks17.0 weeks
Appeals lodged / allowed1 / 2—

All projects in Stirling

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.