Solar, wind and battery projects near Huddersfield (HD5)
33 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of HD5 (Kirklees): 1 is waiting for a planning decision, 31 approved but not yet running. The largest live scheme is Ashday Hall Farm, Ashday Lane (65 MW battery storage, approved on 12 March 2025, not yet built), 7.3 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of HD5
Projects of 1 MW and more (8)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Aflex Hose, Dyson Wood Way - olar Panelsrooftop solar | rooftop solar | 1.1 | approved, not builtupdated Jun 2024 | Apr 2024 | granted Jun 2024 | Jun 2024 | Kirklees | 3.5 |
| Lowfields Energy Storage Projectbattery storage | battery storage | 49.9 | approved, not built may be out of dateupdated Oct 2025 | Dec 2022 | granted Mar 2023 | Oct 2025 | Calderdale | 7.2 |
| Ashday Hall Farm, Ashday Lanebattery storage | battery storage | 65 | approved, not builtupdated Mar 2025 | Aug 2024 | granted Mar 2025 | Mar 2025 | Calderdale | 7.3 |
| Low Farm, Flockton Solar Photovoltaic Farmsolar farm | solar farm | 49.9 | approved, not built may be out of dateupdated Sep 2025 | Sep 2021 | granted Aug 2022 | Sep 2025 | Wakefield | 7.8 |
| New Hall Farm, New Hall Lane Solar Farmsolar farm | solar farm | 22.4 | approved, not builtupdated Jun 2026 | Oct 2023 | granted Jun 2025 | Jun 2026 | Wakefield | 9.0 |
| Stainland Road, Salterhebblebattery storage | battery storage | 25 | approved, not built may be out of dateupdated Apr 2025 | Jun 2021 | granted Sep 2021 | Apr 2025 | Calderdale | 9.0 |
| Dewsbury Sewage, Clough Lanesolar farm | solar farm | 1 | approved, not builtupdated Jun 2026 | Jul 2024 | granted May 2026 | Jun 2026 | Wakefield | 9.9 |
| Dearne Head Wind Farmwind farm | wind farm | 8 | refusedupdated Aug 2013 | Jan 2013 | refused Aug 2013 | Aug 2013 | Kirklees | 10.0 |
Smaller schemes under 1 MW, mostly rooftop solar (25)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| John Smiths Stadium, Huddersfield Townrooftop solar | rooftop solar | 0.5 | approved, not builtupdated Sep 2025 | Jul 2025 | granted Sep 2025 | Sep 2025 | Kirklees | 1.7 |
| Huddersfield Town Sports Academy, Leeds Roadrooftop solar | rooftop solar | 0.1 | approved, not builtupdated Sep 2025 | Jul 2025 | granted Sep 2025 | Sep 2025 | Kirklees | 1.8 |
| Cummins Turbo Technologies, St Andrews Roadrooftop solar | rooftop solar | 0.5 | approved, not builtupdated Jul 2024 | May 2024 | granted Jul 2024 | Jul 2024 | Kirklees | 1.9 |
| Cummins Turbo Technologies, St Andrews Roadrooftop solar | rooftop solar | 0.9 | approved, not builtupdated Jul 2023 | Jun 2023 | granted Jul 2023 | Jul 2023 | Kirklees | 1.9 |
| Cummins Turbo Technology, St Andrews Road Solar PV Canopiessolar farm | solar farm | — | application submittedupdated May 2026 | Mar 2026 | — | May 2026 | Kirklees | 1.9 |
| United Anodisers, Red Doles Lanerooftop solar | rooftop solar | 0.3 | under constructionupdated Apr 2023 | Dec 2022 | — | Apr 2023 | Kirklees | 2.1 |
| University Of Huddersfield, Queensgaterooftop solar | rooftop solar | 0.7 | approved, not built may be out of dateupdated Apr 2023 | Dec 2022 | granted Feb 2023 | Apr 2023 | Kirklees | 2.1 |
| University Of Huddersfield, Queensgaterooftop solar | rooftop solar | 0.2 | approved, not builtupdated Dec 2025 | Sep 2025 | granted Nov 2025 | Dec 2025 | Kirklees | 2.2 |
| Ellis Hill Trading Estate, Leeds Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Jul 2024 | May 2024 | granted Jul 2024 | Jul 2024 | Kirklees | 2.4 |
| Huddersfield Audi, Leeds Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Jan 2026 | Oct 2025 | granted Dec 2025 | Jan 2026 | Kirklees | 2.4 |
| Aflex House, Dyson Wood Wayrooftop solar | rooftop solar | 0.9 | approved, not builtupdated Apr 2023 | Nov 2022 | granted Jan 2023 | Apr 2023 | Kirklees | 3.6 |
| Newsome Academy, Castle Avenuerooftop solar | rooftop solar | — | approved, not builtupdated Apr 2026 | Mar 2025 | granted Jun 2026 | Apr 2026 | Kirklees | 3.6 |
| Continental Sports, Millgaterooftop solar | rooftop solar | 0.3 | approved, not builtupdated Jun 2023 | Feb 2023 | granted Apr 2023 | Jun 2023 | Kirklees | 3.8 |
| David Brown Santasalo, Park Roadrooftop solar | rooftop solar | 0.6 | approved, not builtupdated Jan 2023 | Aug 2022 | granted Oct 2022 | Jan 2023 | Kirklees | 4.0 |
| Huddersfield Royal Infirmary, Acre Streetrooftop solar | rooftop solar | 0.2 | approved, not builtupdated May 2026 | Feb 2026 | granted Mar 2026 | May 2026 | Kirklees | 4.7 |
| Station Road Energy Storage Facilitybattery storage | battery storage | — | approved, not built may be out of dateupdated May 2024 | Aug 2021 | granted Mar 2022 | May 2024 | Kirklees | 4.9 |
| Yorkshire Building Society, Plover Roadrooftop solar | rooftop solar | 0.2 | approved, not built may be out of dateupdated Jul 2023 | May 2023 | granted Jul 2023 | Jul 2023 | Kirklees | 5.3 |
| Wesco Aircraft Emea, Leeds Roadrooftop solar | rooftop solar | 0.3 | approved, not builtupdated May 2024 | Feb 2024 | granted Apr 2024 | May 2024 | Kirklees | 5.6 |
| Spire Elland Hospitalrooftop solar | rooftop solar | 0.2 | approved, not builtupdated May 2025 | Dec 2024 | granted Apr 2025 | May 2025 | Calderdale | 7.1 |
| Lowfields Business Park, Lowfields Wayrooftop solar | rooftop solar | 0.6 | approved, not builtupdated Aug 2023 | Jun 2023 | granted Aug 2023 | Aug 2023 | Calderdale | 7.2 |
| Low Farm, Flocktonbattery storage | battery storage | — | approved, not built may be out of dateupdated Sep 2025 | Sep 2021 | granted Aug 2022 | Sep 2025 | Wakefield | 7.8 |
| Thornton And Ross, Manchester Roadrooftop solar | rooftop solar | 0.5 | approved, not built may be out of dateupdated Jun 2023 | Jun 2023 | granted Jul 2023 | Jun 2023 | Kirklees | 7.9 |
| Calder Textiles, Dewsbury Mills Solar Photovoltaic Equipmentrooftop solar | rooftop solar | — | approved, not builtupdated Aug 2023 | Jun 2023 | granted Aug 2023 | Aug 2023 | Kirklees | 8.0 |
| H M Prison & Young Offender Institutionsolar farm | solar farm | 0.2 | approved, not builtupdated Dec 2021 | Oct 2021 | granted Dec 2021 | Dec 2021 | Wakefield | 8.9 |
| Sainsburys, Railway Streetrooftop solar | rooftop solar | 0.4 | approved, not builtupdated May 2026 | Feb 2026 | granted Apr 2026 | May 2026 | Kirklees | 9.3 |
Distance from the average position of the HD5 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 5 | 1 | 4 | 0 | 0 | 73.5 |
| Rooftop solar | 22 | 0 | 22 | 0 | 0 | 8.9 |
| Wind farm | 1 | 0 | 0 | 0 | 1 | 0 |
| Battery storage | 5 | 0 | 5 | 0 | 0 | 140 |
MW in pipeline: pending, approved and under-construction capacity.
How Kirklees decides solar, wind and battery applications
| Applications | Kirklees | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 26 | 10,236 |
| Refused | 2 (8%) | 19% |
| Solar refused | 0 of 22 | 12% |
| Onshore wind refused | 2 of 2 | 45% |
| Battery storage refused | 0 of 2 | 16% |
| Median time from submission to decision | 7.9 weeks | 17.0 weeks |
| Appeals lodged / allowed | 0 / 1 | — |
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near HD5, 8 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.