Ashday Hall Farm, Ashday Lane (65 MW battery storage)

Ashday Hall Farm, Ashday Lane is a 65 MW battery storage project in Calderdale, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 12 March 2025, not yet built; the record was last updated on 24 March 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

65 MWbattery storage
approved, not builtstatus in REPD
24 March 2025record last updated
Calderdalecouncil area

Planning timeline

DateStage
9 August 2024Application submitted
12 March 2025Planning permission granted
12 March 2028Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
65 MW
Status (REPD)
approved, not built
Record last updated
24 March 2025
Operator or applicant
Sandbrook Capital Bes Limited
Planning authority
Calderdale
Planning application reference
24/00680/FUL
Address (REPD)
Ashday Hall Farm, Ashday Lane, Halifax, Elland
Council area (by location)
Calderdale
Time to decision
31 weeks
Name in REPD
Ashday Hall Farm, Ashday Lane - Battery Energy Storage
REPD reference
16909

Who decides

ApplicationsCalderdaleUK
Decided applications (solar, wind, battery)1810,236
Refused3 (17%)19%
Solar refused0 of 612%
Onshore wind refused3 of 645%
Battery storage refused0 of 616%
Median time from submission to decision15.1 weeks17.0 weeks
Appeals lodged / allowed1 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Lowfields Energy Storage Projectbattery storage49.9approved, not built0.8
Stainland Road, Salterhebblebattery storage25approved, not built2.6
Swales Moor Farmbattery storage5permission expired6.3
Stainland Roadbattery storage20application withdrawn6.6
Holmfield Battery Storagebattery storage500approved, not built7.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.6983, -1.817).