Energy Projects Near You

Solar, wind and battery projects near Elland (HX5)

36 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of HX5 (Calderdale): 1 is waiting for a planning decision, 31 approved but not yet running. The largest live scheme is Holmfield Battery Storage (500 MW battery storage, approved on 29 May 2025, not yet built), 8.6 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

36projects within 10 km
1awaiting a decision
31approved, not running
0operational

Projects within 10 km of HX5

Projects of 1 MW and more (8)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Lowfields Energy Storage Projectbattery storagebattery storage49.9approved, not built may be out of dateupdated Oct 2025Dec 2022granted Mar 2023Oct 2025Calderdale1.1
Stainland Road, Salterhebblebattery storagebattery storage25approved, not built may be out of dateupdated Apr 2025Jun 2021granted Sep 2021Apr 2025Calderdale1.9
Ashday Hall Farm, Ashday Lanebattery storagebattery storage65approved, not builtupdated Mar 2025Aug 2024granted Mar 2025Mar 2025Calderdale1.9
Aflex Hose, Dyson Wood Way - olar Panelsrooftop solarrooftop solar1.1approved, not builtupdated Jun 2024Apr 2024granted Jun 2024Jun 2024Kirklees4.7
Stainland Roadbattery storagebattery storage20application withdrawnupdated Oct 2018Sep 2017—Oct 2018Calderdale5.0
Swales Moor Farmbattery storagebattery storage5permission expiredupdated Mar 2020Mar 2020granted Aug 2020Mar 2020Calderdale7.2
Holmfield Battery Storagebattery storagebattery storage500approved, not builtupdated Jun 2025Dec 2024granted May 2025Jun 2025Calderdale8.6
Slaithwaite Moor Community Wind Farmwind farmwind farm6.9application withdrawnupdated Jul 2015Dec 2013—Jul 2015Kirklees9.1
Smaller schemes under 1 MW, mostly rooftop solar (28)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Spire Elland Hospitalrooftop solarrooftop solar0.2approved, not builtupdated May 2025Dec 2024granted Apr 2025May 2025Calderdale0.6
Lowfields Business Park, Lowfields Wayrooftop solarrooftop solar0.6approved, not builtupdated Aug 2023Jun 2023granted Aug 2023Aug 2023Calderdale1.4
Yorkshire Building Society, Plover Roadrooftop solarrooftop solar0.2approved, not built may be out of dateupdated Jul 2023May 2023granted Jul 2023Jul 2023Kirklees3.4
Huddersfield Royal Infirmary, Acre Streetrooftop solarrooftop solar0.2approved, not builtupdated May 2026Feb 2026granted Mar 2026May 2026Kirklees3.5
Eureka, Discovery Roadrooftop solarrooftop solar0.2approved, not builtupdated May 2024Mar 2024granted Apr 2024May 2024Calderdale4.2
Aflex House, Dyson Wood Wayrooftop solarrooftop solar0.9approved, not builtupdated Apr 2023Nov 2022granted Jan 2023Apr 2023Kirklees4.5
Sainsburys, Wade Streetrooftop solarrooftop solar0.8approved, not builtApr 2026granted Jun 2026—Calderdale4.8
United Anodisers, Red Doles Lanerooftop solarrooftop solar0.3under constructionupdated Apr 2023Dec 2022—Apr 2023Kirklees5.2
Continental Sports, Millgaterooftop solarrooftop solar0.3approved, not builtupdated Jun 2023Feb 2023granted Apr 2023Jun 2023Kirklees5.3
John Smiths Stadium, Huddersfield Townrooftop solarrooftop solar0.5approved, not builtupdated Sep 2025Jul 2025granted Sep 2025Sep 2025Kirklees5.5
Huddersfield Town Sports Academy, Leeds Roadrooftop solarrooftop solar0.1approved, not builtupdated Sep 2025Jul 2025granted Sep 2025Sep 2025Kirklees5.5
Cummins Turbo Technology, St Andrews Road Solar PV Canopiessolar farmsolar farm—application submittedupdated May 2026Mar 2026—May 2026Kirklees5.6
Cummins Turbo Technologies, St Andrews Roadrooftop solarrooftop solar0.9approved, not builtupdated Jul 2023Jun 2023granted Jul 2023Jul 2023Kirklees5.6
Cummins Turbo Technologies, St Andrews Roadrooftop solarrooftop solar0.5approved, not builtupdated Jul 2024May 2024granted Jul 2024Jul 2024Kirklees5.7
University Of Huddersfield, Queensgaterooftop solarrooftop solar0.2approved, not builtupdated Dec 2025Sep 2025granted Nov 2025Dec 2025Kirklees5.9
David Brown Santasalo, Park Roadrooftop solarrooftop solar0.6approved, not builtupdated Jan 2023Aug 2022granted Oct 2022Jan 2023Kirklees5.9
University Of Huddersfield, Queensgaterooftop solarrooftop solar0.7approved, not built may be out of dateupdated Apr 2023Dec 2022granted Feb 2023Apr 2023Kirklees5.9
Ellis Hill Trading Estate, Leeds Roadrooftop solarrooftop solar0.2approved, not builtupdated Jul 2024May 2024granted Jul 2024Jul 2024Kirklees5.9
Huddersfield Audi, Leeds Roadrooftop solarrooftop solar0.2approved, not builtupdated Jan 2026Oct 2025granted Dec 2025Jan 2026Kirklees6.1
Ryburn Valley High School, St Peters Avenuerooftop solarrooftop solar0.3approved, not builtupdated Sep 2024Jul 2024granted Sep 2024Sep 2024Calderdale6.7
Thornton And Ross, Manchester Roadrooftop solarrooftop solar0.5approved, not built may be out of dateupdated Jun 2023Jun 2023granted Jul 2023Jun 2023Kirklees6.7
Newsome Academy, Castle Avenuerooftop solarrooftop solar—approved, not builtupdated Apr 2026Mar 2025granted Jun 2026Apr 2026Kirklees7.2
Appleton Academy, Woodside Roadrooftop solarrooftop solar0.2approved, not builtupdated Nov 2024Sep 2024granted Nov 2024Nov 2024Bradford7.7
Rishworth School, Oldham Roadrooftop solarrooftop solar0.2application withdrawnupdated Sep 2024Apr 2024—Sep 2024Calderdale7.9
Holmfieldbattery storagebattery storage0.2under constructionupdated Jul 2022Jul 2022granted Mar 2023Jul 2022Bradford8.5
Holmfield Industrial Estate Energy Storage Facilitybattery storagebattery storage—approved, not builtupdated Nov 2025Jul 2024granted Oct 2025Nov 2025Calderdale8.6
Wesco Aircraft Emea, Leeds Roadrooftop solarrooftop solar0.3approved, not builtupdated May 2024Feb 2024granted Apr 2024May 2024Kirklees8.6
Sedbergh Sports and Leisure Centrerooftop solarrooftop solar0.2under constructionupdated Apr 2026——Apr 2026Bradford9.8

Distance from the average position of the HX5 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm110000
Rooftop solar260250010.2
Wind farm100000
Battery storage80600640

MW in pipeline: pending, approved and under-construction capacity.

How Calderdale decides solar, wind and battery applications

ApplicationsCalderdaleUK
Decided applications (solar, wind, battery)1810,236
Refused3 (17%)19%
Solar refused0 of 612%
Onshore wind refused3 of 645%
Battery storage refused0 of 616%
Median time from submission to decision15.1 weeks17.0 weeks
Appeals lodged / allowed1 / 0—

All projects in Calderdale

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near HX5, 5 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.