Renewable energy projects in Calderdale

20 solar, wind or battery projects of 150 kW or more are located in Calderdale (REPD, July 2026 extract): 0 pending, 11 approved but not running, 4 operational and 1 refused. The council refused 3 of 18 decided applications (17%; UK 19%), with a median 15 weeks from submission to decision.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

20projects in the council area
0awaiting a decision
11approved, not running
17%of decisions refused

How Calderdale decides

ApplicationsCalderdaleUK
Decided applications (solar, wind, battery)1810,236
Refused3 (17%)19%
Solar refused0 of 612%
Onshore wind refused3 of 645%
Battery storage refused0 of 616%
Median time from submission to decision15.1 weeks17.0 weeks
Appeals lodged / allowed1 / 0—

Projects in Calderdale

Projects of 1 MW and more (12)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updated
Holmfield Battery Storagebattery storagebattery storage500approved, not builtupdated Jun 2025Dec 2024granted May 2025Jun 2025
Ashday Hall Farm, Ashday Lanebattery storagebattery storage65approved, not builtupdated Mar 2025Aug 2024granted Mar 2025Mar 2025
Lowfields Energy Storage Projectbattery storagebattery storage49.9approved, not built may be out of dateupdated Oct 2025Dec 2022granted Mar 2023Oct 2025
Stainland Road, Salterhebblebattery storagebattery storage25approved, not built may be out of dateupdated Apr 2025Jun 2021granted Sep 2021Apr 2025
Crook Hill (Rochdale MBC) 2 of 2wind farmwind farm23.8operationalupdated Jan 2016Jul 2008granted Jul 2009Jan 2016
Stainland Roadbattery storagebattery storage20application withdrawnupdated Oct 2018Sep 2017—Oct 2018
Ovenden Moor (Repower)wind farmwind farm18operationalupdated Feb 2017Aug 2012granted Nov 2012Feb 2017
Coal Clough Wind Farm Repoweringwind farmwind farm16operationalupdated May 2015Dec 2009granted Jan 2013May 2015
Coal Clough Wind Farmwind farmwind farm9.6operationalupdated Jun 2010Nov 1991granted Jul 1992Jun 2010
Ovenden Moorwind farmwind farm9.2decommissionedupdated Dec 2015—granted Jul 1992Dec 2015
Swales Moor Farmbattery storagebattery storage5permission expiredupdated Mar 2020Mar 2020granted Aug 2020Mar 2020
Tooter Hill and Hogshead Hillwind farmwind farm3refusedupdated Oct 2013Jan 1999refused Jun 1999Oct 2013
Smaller schemes under 1 MW, mostly rooftop solar (8)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updated
Sainsburys, Wade Streetrooftop solarrooftop solar0.8approved, not builtApr 2026granted Jun 2026—
Sandholme Iron Works, Halifax Roadrooftop solarrooftop solar0.8approved, not builtupdated Feb 2024Jan 2024granted Feb 2024Feb 2024
Lowfields Business Park, Lowfields Wayrooftop solarrooftop solar0.6approved, not builtupdated Aug 2023Jun 2023granted Aug 2023Aug 2023
Ryburn Valley High School, St Peters Avenuerooftop solarrooftop solar0.3approved, not builtupdated Sep 2024Jul 2024granted Sep 2024Sep 2024
Eureka, Discovery Roadrooftop solarrooftop solar0.2approved, not builtupdated May 2024Mar 2024granted Apr 2024May 2024
Rishworth School, Oldham Roadrooftop solarrooftop solar0.2application withdrawnupdated Sep 2024Apr 2024—Sep 2024
Spire Elland Hospitalrooftop solarrooftop solar0.2approved, not builtupdated May 2025Dec 2024granted Apr 2025May 2025
Holmfield Industrial Estate Energy Storage Facilitybattery storagebattery storage—approved, not builtupdated Nov 2025Jul 2024granted Oct 2025Nov 2025

Postcode districts in Calderdale

DistrictProjects within 10 kmPendingApprovedOperational
HD6452380
HX1372281
HX2271201
HX3523411
HX4331280
HX5361310
HX6200141
HX713153
OL1418146

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Projects belong to Calderdale by location (nearest postcode to the REPD grid reference); decisions are counted by the planning authority named in REPD.