Coal Clough Wind Farm (9.6 MW)

Coal Clough Wind Farm is a 9.6 MW wind farm project in Calderdale, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 February 1993; the record was last updated on 9 June 2010.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

9.6 MWwind farm
operationalstatus in REPD
9 June 2010record last updated
Calderdalecouncil area

Planning timeline

DateStage
25 November 1991Application submitted
3 July 1992Planning permission granted
1 February 1993Operational

Project details

Technology
wind farm
Capacity
9.6 MW
Status (REPD)
operational
Record last updated
9 June 2010
Operator or applicant
Renewable Energy Systems (RES)
Planning authority
Burnley
Planning application reference
91/0920 & APP/2005/0867
Turbines
24
Address (REPD)
Burnley
Council area (by location)
Calderdale
Time to decision
32 weeks
REPD reference
3079

Who decides

ApplicationsBurnleyUK
Decided applications (solar, wind, battery)1710,236
Refused7 (41%)19%
Solar refused0 of 312%
Onshore wind refused4 of 845%
Battery storage refused3 of 616%
Median time from submission to decision24.7 weeks17.0 weeks
Appeals lodged / allowed0 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Coal Clough Wind Farm Repoweringwind farm16operational<0.1
Coal Clough Wind Farm (Co-located)solar farm10application submitted0.3
Todmorden Moorwind farm12.3operational5.5
Gorpley Wind Farmwind farm9.2appeal withdrawn5.5
Reaps Moss Wind Farmwind farm10.2operational5.6
Hogshead Wind Farmwind farm7.1refused6.0
White Hillwind farm12refused6.2
Park Road Battery Storagebattery storage10approved, not built7.0
Widow Hill, Balderstone Lanebattery storage70under construction7.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.7497, -2.15).