Energy Projects Near You

Widow Hill, Balderstone Lane (70 MW battery storage)

Widow Hill, Balderstone Lane is a 70 MW battery storage project in Burnley, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: under construction since 1 May 2025; the record was last updated on 22 May 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

70 MWbattery storage
under constructionstatus in REPD
22 May 2025record last updated
Burnleycouncil area

Planning timeline

DateStage
13 July 2021Application submitted
20 July 2023Planning permission granted
1 May 2025Construction started

Project details

Technology
battery storage (stand-alone storage)
Capacity
70 MW
Status (REPD)
under construction
Record last updated
22 May 2025
Operator or applicant
P3P Partners LLP
Planning authority
Burnley
Planning application reference
FUL/2021/0375
Address (REPD)
Balderstone Lane, Burnley
Council area (by location)
Burnley
Time to decision
105 weeks
Name in REPD
Widow Hill, Balderstone Lane - Battery Energy Storage System
REPD reference
9340

Who decides

ApplicationsBurnleyUK
Decided applications (solar, wind, battery)1710,236
Refused7 (41%)19%
Solar refused0 of 312%
Onshore wind refused4 of 845%
Battery storage refused3 of 616%
Median time from submission to decision24.7 weeks17.0 weeks
Appeals lodged / allowed0 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
The Old Vicarage, Reedleybattery storage100approved, not built2.9
Walshaw House, Regent Streetbattery storage100approved, not built5.0
White Hillwind farm12refused5.8
Hameldon Hill Wind Farm (extension 2)wind farm7.1permission expired6.6
Hameldon Hill extensionwind farm7.5operational7.1
Coal Clough Wind Farm (Co-located)solar farm10application submitted7.2
Coal Clough Wind Farm Repoweringwind farm16operational7.4
Coal Clough Wind Farmwind farm9.6operational7.4
Padihambattery storage99.9refused7.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.8046, -2.2142).