White Hill (12 MW wind farm)

White Hill is a 12 MW wind farm project in Burnley, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 18 March 2003; the record was last updated on 10 December 2003.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

12 MWwind farm
refusedstatus in REPD
10 December 2003record last updated
Burnleycouncil area

Planning timeline

DateStage
11 December 2002Application submitted
18 March 2003Refused by the planning authority

Project details

Technology
wind farm
Capacity
12 MW
Status (REPD)
refused
Record last updated
10 December 2003
Operator or applicant
E.ON UK
Planning authority
Burnley
Planning application reference
12/02/656
Appeal reference
APP/Z2315/A/03/1114592
Address (REPD)
West of Crown Point Car Park , Crown Point Road , Burnley
Council area (by location)
Burnley
Time to decision
14 weeks
REPD reference
3499

Who decides

ApplicationsBurnleyUK
Decided applications (solar, wind, battery)1710,236
Refused7 (41%)19%
Solar refused0 of 312%
Onshore wind refused4 of 845%
Battery storage refused3 of 616%
Median time from submission to decision24.7 weeks17.0 weeks
Appeals lodged / allowed0 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Hameldon Hill Wind Farm (extension 2)wind farm7.1permission expired2.9
Hameldon Hill extensionwind farm7.5operational4.4
Widow Hill, Balderstone Lanebattery storage70under construction5.8
Coal Clough Wind Farm (Co-located)solar farm10application submitted6.0
Huncoat Power Stationbattery storage45refused6.2
Coal Clough Wind Farm Repoweringwind farm16operational6.2
Coal Clough Wind Farmwind farm9.6operational6.2
Shuttleworth House, Higher Shuttleworthbattery storage100refused6.4
The Old Vicarage, Reedleybattery storage100approved, not built6.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.7553, -2.2441).