Energy Projects Near You

Solar, wind and battery projects near Todmorden (OL14)

18 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of OL14 (Calderdale): 1 is waiting for a planning decision, 4 approved but not yet running, 6 operational. The largest live scheme is Coal Clough Wind Farm (Co-located) (10 MW solar farm, application submitted on 24 September 2019, no decision recorded; REPD status may be out of date), 5.3 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

18projects within 10 km
1awaiting a decision
4approved, not running
6operational

Projects within 10 km of OL14

Projects of 1 MW and more (15)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Gorpley Wind Farmwind farmwind farm9.2appeal withdrawnupdated Oct 2015Feb 2014refused Oct 2014Oct 2015Rossendale4.0
Todmorden Moorwind farmwind farm12.3operationalupdated Jun 2015Sep 2010granted Apr 2011Jun 2015Rossendale4.1
Tooter Hill and Hogshead Hillwind farmwind farm3refusedupdated Oct 2013Jan 1999refused Jun 1999Oct 2013Calderdale4.4
Reaps Moss Wind Farmwind farmwind farm10.2operationalupdated Feb 2016Feb 2007granted Oct 2009Feb 2016Rossendale4.6
Hogshead Wind Farmwind farmwind farm7.1refusedupdated Oct 2013Jun 1999refused Feb 2000Oct 2013Rossendale4.7
Crook Hill (Rochdale MBC) 2 of 2wind farmwind farm23.8operationalupdated Jan 2016Jul 2008granted Jul 2009Jan 2016Calderdale5.0
Coal Clough Wind Farm Repoweringwind farmwind farm16operationalupdated May 2015Dec 2009granted Jan 2013May 2015Calderdale5.1
Coal Clough Wind Farmwind farmwind farm9.6operationalupdated Jun 2010Nov 1991granted Jul 1992Jun 2010Calderdale5.1
Black Scout Wind Farmwind farmwind farm2refusedupdated Sep 2003Jan 2000refused May 2000Sep 2003Burnley5.1
Crook Hill (Calderdale MBC) 1 of 2wind farmwind farm13.6operationalupdated Jan 2016Aug 2008granted Oct 2009Jan 2016Rochdale5.2
Coal Clough Wind Farm (Co-located)solar farmsolar farm10application submitted may be out of dateupdated Jan 2021Sep 2019—Jan 2021Burnley5.3
Warcock Hill Projectwind farmwind farm1refusedupdated Sep 2004Jan 2000refused May 2000Sep 2004Burnley5.8
Park Road Battery Storagebattery storagebattery storage10approved, not built may be out of dateupdated Sep 2022Jul 2021granted Nov 2021Sep 2022Rossendale7.0
Great Hill Wind Farmwind farmwind farm10.1refusedupdated Dec 2004Jun 1999refused Mar 2000Dec 2004Rochdale7.7
Rooley Moorwind farmwind farm39.6appeal withdrawnupdated Jan 2016Aug 2014refused Jul 2015Jan 2016Rochdale9.8
Smaller schemes under 1 MW, mostly rooftop solar (3)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Sandholme Iron Works, Halifax Roadrooftop solarrooftop solar0.8approved, not builtupdated Feb 2024Jan 2024granted Feb 2024Feb 2024Calderdale1.0
Corrosion Resistant Products, Todmorden Roadrooftop solarrooftop solar0.3approved, not builtupdated Mar 2025Jan 2025granted Feb 2025Mar 2025Rochdale7.3
Makin Metal Powders Limited, Buckley Roadrooftop solarrooftop solar0.7approved, not builtupdated Sep 2023Jun 2023granted Sep 2023Sep 2023Rochdale9.6

Distance from the average position of the OL14 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm1100010
Rooftop solar303001.7
Wind farm1300650
Battery storage1010010

MW in pipeline: pending, approved and under-construction capacity.

How Calderdale decides solar, wind and battery applications

ApplicationsCalderdaleUK
Decided applications (solar, wind, battery)1810,236
Refused3 (17%)19%
Solar refused0 of 612%
Onshore wind refused3 of 645%
Battery storage refused0 of 616%
Median time from submission to decision15.1 weeks17.0 weeks
Appeals lodged / allowed1 / 0—

All projects in Calderdale

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near OL14, 2 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.