Solar, wind and battery projects near Hebden Bridge (HX7)
13 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of HX7 (Calderdale): 1 is waiting for a planning decision, 5 approved but not yet running, 3 operational. The largest live scheme is Holmfield Battery Storage (500 MW battery storage, approved on 29 May 2025, not yet built), 9.2 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of HX7
Projects of 1 MW and more (8)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Ovenden Moorwind farm | wind farm | 9.2 | decommissionedupdated Dec 2015 | — | granted Jul 1992 | Dec 2015 | Calderdale | 6.1 |
| Ovenden Moor (Repower)wind farm | wind farm | 18 | operationalupdated Feb 2017 | Aug 2012 | granted Nov 2012 | Feb 2017 | Calderdale | 6.6 |
| Holmfield Battery Storagebattery storage | battery storage | 500 | approved, not builtupdated Jun 2025 | Dec 2024 | granted May 2025 | Jun 2025 | Calderdale | 9.2 |
| Coal Clough Wind Farm Repoweringwind farm | wind farm | 16 | operationalupdated May 2015 | Dec 2009 | granted Jan 2013 | May 2015 | Calderdale | 9.4 |
| Coal Clough Wind Farmwind farm | wind farm | 9.6 | operationalupdated Jun 2010 | Nov 1991 | granted Jul 1992 | Jun 2010 | Calderdale | 9.4 |
| Swales Moor Farmbattery storage | battery storage | 5 | permission expiredupdated Mar 2020 | Mar 2020 | granted Aug 2020 | Mar 2020 | Calderdale | 9.5 |
| Stainland Roadbattery storage | battery storage | 20 | application withdrawnupdated Oct 2018 | Sep 2017 | — | Oct 2018 | Calderdale | 9.6 |
| Coal Clough Wind Farm (Co-located)solar farm | solar farm | 10 | application submitted may be out of dateupdated Jan 2021 | Sep 2019 | — | Jan 2021 | Burnley | 9.7 |
Smaller schemes under 1 MW, mostly rooftop solar (5)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Sandholme Iron Works, Halifax Roadrooftop solar | rooftop solar | 0.8 | approved, not builtupdated Feb 2024 | Jan 2024 | granted Feb 2024 | Feb 2024 | Calderdale | 5.7 |
| Ryburn Valley High School, St Peters Avenuerooftop solar | rooftop solar | 0.3 | approved, not builtupdated Sep 2024 | Jul 2024 | granted Sep 2024 | Sep 2024 | Calderdale | 6.4 |
| Holmfield Industrial Estate Energy Storage Facilitybattery storage | battery storage | — | approved, not builtupdated Nov 2025 | Jul 2024 | granted Oct 2025 | Nov 2025 | Calderdale | 9.1 |
| Rishworth School, Oldham Roadrooftop solar | rooftop solar | 0.2 | application withdrawnupdated Sep 2024 | Apr 2024 | — | Sep 2024 | Calderdale | 9.3 |
| Holmfieldbattery storage | battery storage | 0.2 | under constructionupdated Jul 2022 | Jul 2022 | granted Mar 2023 | Jul 2022 | Bradford | 9.6 |
Distance from the average position of the HX7 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 1 | 1 | 0 | 0 | 0 | 10 |
| Rooftop solar | 3 | 0 | 2 | 0 | 0 | 1.1 |
| Wind farm | 4 | 0 | 0 | 3 | 0 | 0 |
| Battery storage | 5 | 0 | 3 | 0 | 0 | 500 |
MW in pipeline: pending, approved and under-construction capacity.
How Calderdale decides solar, wind and battery applications
| Applications | Calderdale | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 18 | 10,236 |
| Refused | 3 (17%) | 19% |
| Solar refused | 0 of 6 | 12% |
| Onshore wind refused | 3 of 6 | 45% |
| Battery storage refused | 0 of 6 | 16% |
| Median time from submission to decision | 15.1 weeks | 17.0 weeks |
| Appeals lodged / allowed | 1 / 0 | — |
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near HX7, 1 project has a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.