Solar, wind and battery projects near Halifax (HX4)
33 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of HX4 (Calderdale): 1 is waiting for a planning decision, 28 approved but not yet running. The largest live scheme is Holmfield Battery Storage (500 MW battery storage, approved on 29 May 2025, not yet built), 9.1 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of HX4
Projects of 1 MW and more (8)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Stainland Roadbattery storage | battery storage | 20 | application withdrawnupdated Oct 2018 | Sep 2017 | — | Oct 2018 | Calderdale | 1.8 |
| Stainland Road, Salterhebblebattery storage | battery storage | 25 | approved, not built may be out of dateupdated Apr 2025 | Jun 2021 | granted Sep 2021 | Apr 2025 | Calderdale | 2.7 |
| Lowfields Energy Storage Projectbattery storage | battery storage | 49.9 | approved, not built may be out of dateupdated Oct 2025 | Dec 2022 | granted Mar 2023 | Oct 2025 | Calderdale | 4.2 |
| Ashday Hall Farm, Ashday Lanebattery storage | battery storage | 65 | approved, not builtupdated Mar 2025 | Aug 2024 | granted Mar 2025 | Mar 2025 | Calderdale | 4.9 |
| Slaithwaite Moor Community Wind Farmwind farm | wind farm | 6.9 | application withdrawnupdated Jul 2015 | Dec 2013 | — | Jul 2015 | Kirklees | 6.6 |
| Aflex Hose, Dyson Wood Way - olar Panelsrooftop solar | rooftop solar | 1.1 | approved, not builtupdated Jun 2024 | Apr 2024 | granted Jun 2024 | Jun 2024 | Kirklees | 7.7 |
| Swales Moor Farmbattery storage | battery storage | 5 | permission expiredupdated Mar 2020 | Mar 2020 | granted Aug 2020 | Mar 2020 | Calderdale | 7.9 |
| Holmfield Battery Storagebattery storage | battery storage | 500 | approved, not builtupdated Jun 2025 | Dec 2024 | granted May 2025 | Jun 2025 | Calderdale | 9.1 |
Smaller schemes under 1 MW, mostly rooftop solar (25)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Spire Elland Hospitalrooftop solar | rooftop solar | 0.2 | approved, not builtupdated May 2025 | Dec 2024 | granted Apr 2025 | May 2025 | Calderdale | 3.8 |
| Ryburn Valley High School, St Peters Avenuerooftop solar | rooftop solar | 0.3 | approved, not builtupdated Sep 2024 | Jul 2024 | granted Sep 2024 | Sep 2024 | Calderdale | 4.3 |
| Lowfields Business Park, Lowfields Wayrooftop solar | rooftop solar | 0.6 | approved, not builtupdated Aug 2023 | Jun 2023 | granted Aug 2023 | Aug 2023 | Calderdale | 4.4 |
| Yorkshire Building Society, Plover Roadrooftop solar | rooftop solar | 0.2 | approved, not built may be out of dateupdated Jul 2023 | May 2023 | granted Jul 2023 | Jul 2023 | Kirklees | 4.5 |
| Rishworth School, Oldham Roadrooftop solar | rooftop solar | 0.2 | application withdrawnupdated Sep 2024 | Apr 2024 | — | Sep 2024 | Calderdale | 4.7 |
| Huddersfield Royal Infirmary, Acre Streetrooftop solar | rooftop solar | 0.2 | approved, not builtupdated May 2026 | Feb 2026 | granted Mar 2026 | May 2026 | Kirklees | 5.0 |
| Eureka, Discovery Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated May 2024 | Mar 2024 | granted Apr 2024 | May 2024 | Calderdale | 5.1 |
| Sainsburys, Wade Streetrooftop solar | rooftop solar | 0.8 | approved, not built | Apr 2026 | granted Jun 2026 | — | Calderdale | 5.7 |
| Thornton And Ross, Manchester Roadrooftop solar | rooftop solar | 0.5 | approved, not built may be out of dateupdated Jun 2023 | Jun 2023 | granted Jul 2023 | Jun 2023 | Kirklees | 5.9 |
| Continental Sports, Millgaterooftop solar | rooftop solar | 0.3 | approved, not builtupdated Jun 2023 | Feb 2023 | granted Apr 2023 | Jun 2023 | Kirklees | 6.6 |
| David Brown Santasalo, Park Roadrooftop solar | rooftop solar | 0.6 | approved, not builtupdated Jan 2023 | Aug 2022 | granted Oct 2022 | Jan 2023 | Kirklees | 7.0 |
| Aflex House, Dyson Wood Wayrooftop solar | rooftop solar | 0.9 | approved, not builtupdated Apr 2023 | Nov 2022 | granted Jan 2023 | Apr 2023 | Kirklees | 7.6 |
| United Anodisers, Red Doles Lanerooftop solar | rooftop solar | 0.3 | under constructionupdated Apr 2023 | Dec 2022 | — | Apr 2023 | Kirklees | 7.8 |
| Cummins Turbo Technology, St Andrews Road Solar PV Canopiessolar farm | solar farm | — | application submittedupdated May 2026 | Mar 2026 | — | May 2026 | Kirklees | 7.8 |
| University Of Huddersfield, Queensgaterooftop solar | rooftop solar | 0.2 | approved, not builtupdated Dec 2025 | Sep 2025 | granted Nov 2025 | Dec 2025 | Kirklees | 7.8 |
| Cummins Turbo Technologies, St Andrews Roadrooftop solar | rooftop solar | 0.9 | approved, not builtupdated Jul 2023 | Jun 2023 | granted Jul 2023 | Jul 2023 | Kirklees | 7.8 |
| Cummins Turbo Technologies, St Andrews Roadrooftop solar | rooftop solar | 0.5 | approved, not builtupdated Jul 2024 | May 2024 | granted Jul 2024 | Jul 2024 | Kirklees | 7.8 |
| University Of Huddersfield, Queensgaterooftop solar | rooftop solar | 0.7 | approved, not built may be out of dateupdated Apr 2023 | Dec 2022 | granted Feb 2023 | Apr 2023 | Kirklees | 7.8 |
| John Smiths Stadium, Huddersfield Townrooftop solar | rooftop solar | 0.5 | approved, not builtupdated Sep 2025 | Jul 2025 | granted Sep 2025 | Sep 2025 | Kirklees | 7.9 |
| Huddersfield Town Sports Academy, Leeds Roadrooftop solar | rooftop solar | 0.1 | approved, not builtupdated Sep 2025 | Jul 2025 | granted Sep 2025 | Sep 2025 | Kirklees | 8.2 |
| Newsome Academy, Castle Avenuerooftop solar | rooftop solar | — | approved, not builtupdated Apr 2026 | Mar 2025 | granted Jun 2026 | Apr 2026 | Kirklees | 8.4 |
| Ellis Hill Trading Estate, Leeds Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Jul 2024 | May 2024 | granted Jul 2024 | Jul 2024 | Kirklees | 8.9 |
| Huddersfield Audi, Leeds Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Jan 2026 | Oct 2025 | granted Dec 2025 | Jan 2026 | Kirklees | 9.0 |
| Holmfield Industrial Estate Energy Storage Facilitybattery storage | battery storage | — | approved, not builtupdated Nov 2025 | Jul 2024 | granted Oct 2025 | Nov 2025 | Calderdale | 9.1 |
| Holmfieldbattery storage | battery storage | 0.2 | under constructionupdated Jul 2022 | Jul 2022 | granted Mar 2023 | Jul 2022 | Bradford | 9.2 |
Distance from the average position of the HX4 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 1 | 1 | 0 | 0 | 0 | 0 |
| Rooftop solar | 23 | 0 | 22 | 0 | 0 | 9.5 |
| Wind farm | 1 | 0 | 0 | 0 | 0 | 0 |
| Battery storage | 8 | 0 | 6 | 0 | 0 | 640 |
MW in pipeline: pending, approved and under-construction capacity.
How Calderdale decides solar, wind and battery applications
| Applications | Calderdale | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 18 | 10,236 |
| Refused | 3 (17%) | 19% |
| Solar refused | 0 of 6 | 12% |
| Onshore wind refused | 3 of 6 | 45% |
| Battery storage refused | 0 of 6 | 16% |
| Median time from submission to decision | 15.1 weeks | 17.0 weeks |
| Appeals lodged / allowed | 1 / 0 | — |
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near HX4, 5 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.