Stainland Road (20 MW battery storage)

Stainland Road is a 20 MW battery storage project in Calderdale, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application withdrawn on 8 February 2018; the record was last updated on 19 October 2018.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

20 MWbattery storage
application withdrawnstatus in REPD
19 October 2018record last updated
Calderdalecouncil area

Planning timeline

DateStage
16 September 2017Application submitted
8 February 2018Application withdrawn

Project details

Technology
battery storage (stand-alone storage)
Capacity
20 MW
Status (REPD)
application withdrawn
Record last updated
19 October 2018
Operator or applicant
Sterling Power Group
Planning authority
Calderdale
Planning application reference
16/01216/FUL
Address (REPD)
Land adjacent to, Stainland Road, Elland, Halifax
Council area (by location)
Calderdale
REPD reference
7083

Who decides

ApplicationsCalderdaleUK
Decided applications (solar, wind, battery)1810,236
Refused3 (17%)19%
Solar refused0 of 612%
Onshore wind refused3 of 645%
Battery storage refused0 of 616%
Median time from submission to decision15.1 weeks17.0 weeks
Appeals lodged / allowed1 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Stainland Road, Salterhebblebattery storage25approved, not built4.2
Slaithwaite Moor Community Wind Farmwind farm6.9application withdrawn5.8
Lowfields Energy Storage Projectbattery storage49.9approved, not built5.9
Ashday Hall Farm, Ashday Lanebattery storage65approved, not built6.6
Swales Moor Farmbattery storage5permission expired8.5
Holmfield Battery Storagebattery storage500approved, not built9.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.6758, -1.9096).