Ovenden Moor (Repower) (18 MW wind farm)

Ovenden Moor (Repower) is an 18 MW wind farm project in Calderdale, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 24 January 2017; the record was last updated on 2 February 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

18 MWwind farm
operationalstatus in REPD
2 February 2017record last updated
Calderdalecouncil area

Planning timeline

DateStage
2 August 2012Application submitted
16 November 2012Planning permission granted
21 May 2015Construction started
24 January 2017Operational

Project details

Technology
wind farm
Capacity
18 MW
Status (REPD)
operational
Record last updated
2 February 2017
Operator or applicant
Yorkshire Windpower
Planning authority
Calderdale
Planning application reference
12/00955/WDF
Turbines
9
Turbine height
115 m
Address (REPD)
Withens Road, Wainstalls, Halifax,
Council area (by location)
Calderdale
Time to decision
15 weeks
REPD reference
4408

Earlier applications for this site

ApplicationMWSubmittedOutcome
Ovenden Moor (Repower) 09/00073/WDF2325 March 2009withdrawn 23 April 2012

Who decides

ApplicationsCalderdaleUK
Decided applications (solar, wind, battery)1810,236
Refused3 (17%)19%
Solar refused0 of 612%
Onshore wind refused3 of 645%
Battery storage refused0 of 616%
Median time from submission to decision15.1 weeks17.0 weeks
Appeals lodged / allowed1 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Ovenden Moorwind farm9.2decommissioned0.6
Holmfield Battery Storagebattery storage500approved, not built4.6
Old Allen Road, Wilsdenbattery storage99.9application submitted5.4
Peat Dykes Farm, Harrop Lanebattery storage100approved, not built5.5
Swales Moor Farmbattery storage5permission expired5.8
Bradford West Substation (Harrop Edge Farm)battery storage49.9under construction5.8
Bradford West, Harrop Lane, Wilsdenbattery storage100approved, not built5.9
Lane Sidebattery storage100approved, not built6.2
Stor Generation Plantbattery storage12approved, not built9.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.7789, -1.9333).