Energy Projects Near You

Bradford West Substation (Harrop Edge Farm) (49.9 MW battery storage)

Bradford West Substation (Harrop Edge Farm) is a 49.9 MW battery storage project in Bradford, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: under construction since 7 July 2022; the record was last updated on 8 July 2022.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWbattery storage
under constructionstatus in REPD
8 July 2022record last updated
Bradfordcouncil area

Planning timeline

DateStage
14 April 2020Application submitted
24 July 2020Planning permission granted
7 July 2022Construction started

Project details

Technology
battery storage (stand-alone storage)
Capacity
49.9 MW
Status (REPD)
under construction
Record last updated
8 July 2022
Operator or applicant
UK Battery Storage
Planning authority
Bradford
Planning application reference
18/03894/OUT
Address (REPD)
Land At Grid Ref 409233 434810 Old Allen Road Wilsden Bradford
Council area (by location)
Bradford
Time to decision
14 weeks
REPD reference
7577

Earlier applications for this site

ApplicationMWSubmittedOutcome
Harrop Edge Farm 18/01635/OUT—20 April 2018withdrawn 13 July 2018
Bradford West Substation (Harrop Edge Farm) 18/03894/OUT49.914 April 2020under construction since 7 July 2022

Who decides

ApplicationsBradfordUK
Decided applications (solar, wind, battery)3710,236
Refused2 (5%)19%
Solar refused0 of 2612%
Onshore wind refused1 of 145%
Battery storage refused1 of 1016%
Median time from submission to decision8.0 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Bradford West, Harrop Lane, Wilsdenbattery storage100approved, not built0.1
Peat Dykes Farm, Harrop Lanebattery storage100approved, not built0.4
Old Allen Road, Wilsdenbattery storage99.9application submitted0.5
Lane Sidebattery storage100approved, not built0.9
Stor Generation Plantbattery storage12approved, not built4.9
Holmfield Battery Storagebattery storage500approved, not built5.7
Ovenden Moor (Repower)wind farm18operational5.8
Ovenden Moorwind farm9.2decommissioned6.3
Midland Roadbattery storage80approved, not built6.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.8095, -1.8613).