Energy Projects Near You

Lane Side (100 MW battery storage)

Lane Side is a 100 MW battery storage project in Bradford, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 16 July 2025, not yet built; the record was last updated on 19 August 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

100 MWbattery storage
approved, not builtstatus in REPD
19 August 2025record last updated
Bradfordcouncil area

Planning timeline

DateStage
3 October 2024Application submitted
16 July 2025Planning permission granted
16 July 2028Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
100 MW
Status (REPD)
approved, not built
Record last updated
19 August 2025
Operator or applicant
Net Zero Twenty Three Limited
Planning authority
Bradford
Planning application reference
24/04720/MAF
Address (REPD)
S/O Lane Side, Wilsden, Bradford
Council area (by location)
Bradford
Time to decision
41 weeks
Name in REPD
Lane Side - Energy Storage
REPD reference
17416

Who decides

ApplicationsBradfordUK
Decided applications (solar, wind, battery)3710,236
Refused2 (5%)19%
Solar refused0 of 2612%
Onshore wind refused1 of 145%
Battery storage refused1 of 1016%
Median time from submission to decision8.0 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Bradford West, Harrop Lane, Wilsdenbattery storage100approved, not built0.8
Bradford West Substation (Harrop Edge Farm)battery storage49.9under construction0.9
Peat Dykes Farm, Harrop Lanebattery storage100approved, not built1.1
Old Allen Road, Wilsdenbattery storage99.9application submitted1.2
Stor Generation Plantbattery storage12approved, not built5.4
Ovenden Moor (Repower)wind farm18operational6.2
Holmfield Battery Storagebattery storage500approved, not built6.6
Ovenden Moorwind farm9.2decommissioned6.8
Midland Roadbattery storage80approved, not built7.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.8174, -1.8642).