Stor Generation Plant (12 MW battery storage)

Stor Generation Plant is a 12 MW battery storage project in Bradford, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 7 April 2025, not yet built; the record was last updated on 7 May 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

12 MWbattery storage
approved, not builtstatus in REPD
7 May 2025record last updated
Bradfordcouncil area

Planning timeline

DateStage
10 February 2025Application submitted
7 April 2025Planning permission granted
7 April 2028Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
12 MW
Status (REPD)
approved, not built
Record last updated
7 May 2025
Operator or applicant
Green Frog Power 214 Limited
Planning authority
Bradford
Planning application reference
24/04887/FUL
Address (REPD)
Stor Generation Plant, Duncombe Road, Bradford
Council area (by location)
Bradford
Time to decision
8 weeks
Name in REPD
Stor Generation Plant - Battery Storage
REPD reference
18096

Earlier applications for this site

ApplicationMWSubmittedOutcome
Stor Generation Plant 21/02041/FUL1216 April 2021replaced by a revised application

Who decides

ApplicationsBradfordUK
Decided applications (solar, wind, battery)3710,236
Refused2 (5%)19%
Solar refused0 of 2612%
Onshore wind refused1 of 145%
Battery storage refused1 of 1016%
Median time from submission to decision8.0 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Midland Roadbattery storage80approved, not built2.4
Bradford West Substation (Harrop Edge Farm)battery storage49.9under construction4.9
Bradford West, Harrop Lane, Wilsdenbattery storage100approved, not built4.9
Old Allen Road, Wilsdenbattery storage99.9application submitted5.1
Peat Dykes Farm, Harrop Lanebattery storage100approved, not built5.2
Lane Sidebattery storage100approved, not built5.4
Holmfield Battery Storagebattery storage500approved, not built6.8
Swales Moor Farmbattery storage5permission expired7.2
Ovenden Moor (Repower)wind farm18operational9.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.7954, -1.7904).