Energy Projects Near You

Crook Hill (Calderdale MBC) 1 of 2 (13.6 MW wind farm)

Crook Hill (Calderdale MBC) 1 of 2 is a 13.6 MW wind farm project in Rochdale, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 December 2015; the record was last updated on 4 January 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

13.6 MWwind farm
operationalstatus in REPD
4 January 2016record last updated
Rochdalecouncil area

Planning timeline

DateStage
4 August 2008Application submitted
12 October 2009Planning permission granted
1 January 2015Construction started
1 December 2015Operational

Project details

Technology
wind farm
Capacity
13.6 MW
Status (REPD)
operational
Record last updated
4 January 2016
Operator or applicant
Infrared Capital Partners
Planning authority
Rochdale
Planning application reference
08/01281/WDF
Turbines
4
Address (REPD)
Crook Hill/Shore Moor, North Of Watergrove Reservoir, Rochdale
Council area (by location)
Rochdale
Time to decision
62 weeks
REPD reference
4354

Earlier applications for this site

ApplicationMWSubmittedOutcome
Crook Hill (Calderdale MBC) 07/00632/WDF1520 March 2007replaced by a revised application

Who decides

ApplicationsRochdaleUK
Decided applications (solar, wind, battery)2610,236
Refused4 (15%)19%
Solar refused0 of 1412%
Onshore wind refused3 of 645%
Battery storage refused1 of 616%
Median time from submission to decision10.6 weeks17.0 weeks
Appeals lodged / allowed1 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Crook Hill (Rochdale MBC) 2 of 2wind farm23.8operational0.3
Great Hill Wind Farmwind farm10.1refused2.7
Gorpley Wind Farmwind farm9.2appeal withdrawn4.7
Hogshead Wind Farmwind farm7.1refused4.7
Todmorden Moorwind farm12.3operational4.8
Reaps Moss Wind Farmwind farm10.2operational5.1
Rooley Moorwind farm39.6appeal withdrawn6.7
Park Road Battery Storagebattery storage10approved, not built6.7
Miall Power Energy Storage Facilitybattery storage5refused6.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.6681, -2.1117).