Energy Projects Near You

Solar, wind and battery projects near Achnacloich (IV46)

2 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of IV46 (Highland): 2 are waiting for a planning decision. The largest live scheme is Ben Aketil Wind Farm - Repowered & Extended (59.4 MW wind farm, application submitted on 9 June 2023, no decision recorded; REPD status may be out of date), 8.7 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

2projects within 10 km
2awaiting a decision
0approved, not running
0operational

Projects within 10 km of IV46

Projects of 1 MW and more (2)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Ben Aketil Wind Farm - Repowered & Extendedwind farmwind farm59.4application submitted may be out of dateupdated Aug 2023Jun 2023—Aug 2023Highland8.7
Ben Aketil Wind Farm - Repowered & Extendedbattery storagebattery storage20application submitted may be out of dateupdated Aug 2023Jun 2023—Aug 2023Highland8.7

Distance from the average position of the IV46 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Wind farm1100059.4
Battery storage1100020

MW in pipeline: pending, approved and under-construction capacity.

How Highland decides solar, wind and battery applications

ApplicationsHighlandUK
Decided applications (solar, wind, battery)16010,236
Refused68 (42%)19%
Solar refused0 of 1512%
Onshore wind refused61 of 11445%
Battery storage refused7 of 3116%
Median time from submission to decision52.3 weeks17.0 weeks
Appeals lodged / allowed20 / 20—

All projects in Highland

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near IV46, 2 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.