Energy Projects Near You

Solar, wind and battery projects near Leicester (LE2)

51 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of LE2 (Leicester): 6 are waiting for a planning decision, 35 approved but not yet running, 7 operational. The largest live scheme is Soars Lodge Farm, Foston Lane Solar Farm (49.9 MW solar farm, approved on 20 March 2026, not yet built), 6.6 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

51projects within 10 km
6awaiting a decision
35approved, not running
7operational

Projects within 10 km of LE2

Projects of 1 MW and more (11)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Blaby Solar Farmsolar farmsolar farm3.5operationalupdated Jul 2016Aug 2015granted Nov 2015Jul 2016Blaby4.7
Dorsey Way, Enderbyrooftop solarrooftop solar1.8approved, not builtupdated Apr 2024Feb 2024granted Apr 2024Apr 2024Blaby5.7
Land at and adjacent to Leicester Forest Servicesbattery storagebattery storage1.5operationalupdated Mar 2020Jun 2017granted Feb 2022Mar 2020Blaby6.2
Sunningdale Roadrooftop solarrooftop solar1.6approved, not builtupdated Aug 2025Jun 2025granted Aug 2025Aug 2025Leicester6.4
Soars Lodge Farm, Foston Lane Solar Farmsolar farmsolar farm49.9approved, not builtupdated May 2026Oct 2024granted Mar 2026May 2026Blaby6.6
National Grid Enderby Substationbattery storagebattery storage57operationalupdated Mar 2026Aug 2020granted Feb 2021Mar 2026Blaby6.8
Enderby Storage, Redcomb Farmbattery storagebattery storage49.9operationalupdated Mar 2026Oct 2017granted Jan 2018Mar 2026Blaby7.3
Pepsico International Limited, Leycroft Roadrooftop solarrooftop solar3.2under constructionupdated Mar 2026Jan 2024granted Mar 2024Mar 2026Leicester7.4
Hoods Closerooftop solarrooftop solar1.7under constructionupdated Aug 2023Apr 2023—Aug 2023Leicester7.5
Land Off Ingarsby Lanesolar farmsolar farm2.1operationalupdated Aug 2016May 2015granted Jul 2015Aug 2016Harborough8.5
Desford Road, Thurlastonsolar farmsolar farm40approved, not built may be out of dateupdated Sep 2020Mar 2018granted Sep 2018Sep 2020Blaby8.6
Smaller schemes under 1 MW, mostly rooftop solar (40)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Granby Road Solar PV Panels & Air Source Heat Pumpsrooftop solarrooftop solar—approved, not built may be out of dateupdated Dec 2021Dec 2021granted Mar 2022Dec 2021Leicester2.3
Madani Schools Federationrooftop solarrooftop solar0.3approved, not built may be out of dateupdated May 2024Feb 2024granted Apr 2024May 2024Leicester2.4
Spire Leicester Hospital, Gartree Roadsolar farmsolar farm0.8approved, not builtupdated Jul 2025Nov 2024granted Jun 2025Jul 2025Oadby and Wigston2.4
Harborough Road Storerooftop solarrooftop solar0.2operationalupdated Apr 2020Dec 2019granted Apr 2020Apr 2020Oadby and Wigston2.6
Parklands Leisure Centre, Washbrook Lanerooftop solarrooftop solar0.2approved, not builtupdated Jul 2025Apr 2025granted Jul 2025Jul 2025Oadby and Wigston2.7
Newarke St Car Parksolar farmsolar farm—under constructionupdated Jun 2022—granted Nov 2023Jun 2022Leicester2.9
Wigston Swimming Pool, Station Roadrooftop solarrooftop solar0.2approved, not builtupdated Nov 2024Oct 2024granted Nov 2024Nov 2024Oadby and Wigston2.9
St Georges Retail Park, St Georges Wayrooftop solarrooftop solar0.4application submittedJun 2026——Leicester3.2
Dysart Way, Birstall Street - Micro Energy Storagebattery storagebattery storage0.2approved, not builtupdated May 2026Feb 2026granted Mar 2026May 2026Leicester4.0
Evington Leisure Centrerooftop solarrooftop solar—approved, not builtupdated Apr 2025Feb 2025granted Mar 2025Apr 2025Leicester4.1
Meridian Leisure Park Solar Photovoltaics Arrayrooftop solarrooftop solar0.2application withdrawnupdated Feb 2022Jan 2022—Feb 2022Blaby4.8
Unit F, Meridian Leisure Park, Braunstone Townrooftop solarrooftop solar—approved, not built may be out of dateupdated Jun 2023May 2023granted Jun 2023Jun 2023Blaby4.8
Showroom Meridian East, Meridian Business Parkrooftop solarrooftop solar0.3approved, not builtupdated Feb 2026Nov 2025granted Jan 2026Feb 2026Blaby4.9
Leicestershire Constabulary, St Johnssolar farmsolar farm0.2approved, not builtupdated Aug 2024Jan 2024granted Jul 2024Aug 2024Blaby4.9
National Space Centrerooftop solarrooftop solar0.2operationalupdated Mar 2019Jan 2019granted Mar 2019Mar 2019Leicester5.3
Humberstone Heights Golf Clubrooftop solarrooftop solar—application withdrawnupdated Jan 2022Sep 2021—Jan 2022Leicester5.3
Centurion Way, Braunstone Townrooftop solarrooftop solar0.2approved, not builtupdated Dec 2021Aug 2021granted Oct 2021Dec 2021Blaby5.3
First Bus Depot, Humphreys Wayrooftop solarrooftop solar0.2application submitted may be out of dateupdated Mar 2023Feb 2023—Mar 2023Leicester5.4
Enderby Road Industrial Estate, Enderby Roadbattery storagebattery storage0.2application submittedupdated Mar 2025Jan 2025—Mar 2025Blaby5.7
Dorsey Way, Enderbyrooftop solarrooftop solar0.7approved, not builtupdated Apr 2024Feb 2024granted Apr 2024Apr 2024Blaby5.7
Rushey Mead Academy, Melton Roadrooftop solarrooftop solar0.3application submittedupdated Mar 2026Jan 2026—Mar 2026Leicester5.7
Gateway College, Colin Grundy Driverooftop solarrooftop solar0.1approved, not builtupdated Dec 2025Oct 2025granted Nov 2025Dec 2025Leicester5.8
Lewisher Road Solar Arraysrooftop solarrooftop solar0.2approved, not builtupdated Sep 2024Jun 2024granted Sep 2024Sep 2024Leicester5.9
Park View Street - Micro Energy Systembattery storagebattery storage0.2approved, not builtupdated Jun 2026Apr 2026granted May 2026Jun 2026Leicester5.9
Langham Roadrooftop solarrooftop solar0.2approved, not builtupdated Nov 2023Sep 2023granted Nov 2023Nov 2023Leicester6.0
The Whittle Estate, Whetstonerooftop solarrooftop solar0.4approved, not builtupdated Nov 2021Sep 2021granted Oct 2021Nov 2021Blaby6.3
Enderby Leisure Centre, Mill Lanebattery storagebattery storage0.2approved, not builtupdated Apr 2025Jan 2025granted Mar 2025Apr 2025Blaby6.4
Feldspar Close - Plot N -Solar Panelsrooftop solarrooftop solar0.3approved, not builtupdated Aug 2025Jun 2025granted Aug 2025Aug 2025Blaby6.5
Orchard Mead Academy, Keyham Lane Westrooftop solarrooftop solar0.3approved, not builtupdated May 2026Jan 2026granted Mar 2026May 2026Leicester6.6
Saladworks, Kirby Muxloerooftop solarrooftop solar0.6approved, not builtupdated Mar 2025Jan 2025granted Mar 2025Mar 2025Blaby6.9
Leisure Centre Carlton Park, King Edward Avenuerooftop solarrooftop solar—approved, not builtupdated Sep 2025Jul 2025granted Sep 2025Sep 2025Blaby6.9
Bingo Club, Beaumont Wayrooftop solarrooftop solar0.4approved, not builtupdated Sep 2023Jul 2023granted Sep 2023Sep 2023Leicester7.4
Forest Roadbattery storagebattery storage—application submittedupdated Nov 2024Sep 2024—Nov 2024Blaby7.4
Lodge Farm Solar Farm & Battery Storagesolar farmsolar farm—application submitted may be out of dateupdated Aug 2025May 2022—Aug 2025Harborough7.7
Lodge Farm Solar Farm & Battery Storagebattery storagebattery storage—approved, not builtupdated Feb 2026May 2022granted Mar 2024Feb 2026Harborough7.7
Ashton Business Park, Ashton Closerooftop solarrooftop solar0.2approved, not builtupdated Aug 2024Jun 2024granted Aug 2024Aug 2024Leicester7.7
Gynsill Lane, Leicester Road - Micro Energy Storagebattery storagebattery storage0.2approved, not builtMar 2026granted May 2026—Charnwood7.8
Roman Avenue, Unit Arooftop solarrooftop solar0.8approved, not builtupdated Mar 2024Jan 2024granted Mar 2024Mar 2024Blaby7.8
Kirby Road Solar Panelsrooftop solarrooftop solar0.5under constructionupdated Jan 2022Nov 2020granted Feb 2021Jan 2022Blaby8.0
Fiona Cairns HQrooftop solarrooftop solar—no application requiredupdated May 2023——May 2023Harborough10.0

Distance from the average position of the LE2 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm8152091
Rooftop solar333252015.1
Battery storage1025301

MW in pipeline: pending, approved and under-construction capacity.

How Leicester decides solar, wind and battery applications

ApplicationsLeicesterUK
Decided applications (solar, wind, battery)1510,236
Refused0 (0%)19%
Solar refused0 of 1312%
Battery storage refused0 of 216%
Median time from submission to decision7.9 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

All projects in Leicester

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near LE2, 6 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.