Solar, wind and battery projects near Leicester (LE2)
51 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of LE2 (Leicester): 6 are waiting for a planning decision, 35 approved but not yet running, 7 operational. The largest live scheme is Soars Lodge Farm, Foston Lane Solar Farm (49.9 MW solar farm, approved on 20 March 2026, not yet built), 6.6 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of LE2
Projects of 1 MW and more (11)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Blaby Solar Farmsolar farm | solar farm | 3.5 | operationalupdated Jul 2016 | Aug 2015 | granted Nov 2015 | Jul 2016 | Blaby | 4.7 |
| Dorsey Way, Enderbyrooftop solar | rooftop solar | 1.8 | approved, not builtupdated Apr 2024 | Feb 2024 | granted Apr 2024 | Apr 2024 | Blaby | 5.7 |
| Land at and adjacent to Leicester Forest Servicesbattery storage | battery storage | 1.5 | operationalupdated Mar 2020 | Jun 2017 | granted Feb 2022 | Mar 2020 | Blaby | 6.2 |
| Sunningdale Roadrooftop solar | rooftop solar | 1.6 | approved, not builtupdated Aug 2025 | Jun 2025 | granted Aug 2025 | Aug 2025 | Leicester | 6.4 |
| Soars Lodge Farm, Foston Lane Solar Farmsolar farm | solar farm | 49.9 | approved, not builtupdated May 2026 | Oct 2024 | granted Mar 2026 | May 2026 | Blaby | 6.6 |
| National Grid Enderby Substationbattery storage | battery storage | 57 | operationalupdated Mar 2026 | Aug 2020 | granted Feb 2021 | Mar 2026 | Blaby | 6.8 |
| Enderby Storage, Redcomb Farmbattery storage | battery storage | 49.9 | operationalupdated Mar 2026 | Oct 2017 | granted Jan 2018 | Mar 2026 | Blaby | 7.3 |
| Pepsico International Limited, Leycroft Roadrooftop solar | rooftop solar | 3.2 | under constructionupdated Mar 2026 | Jan 2024 | granted Mar 2024 | Mar 2026 | Leicester | 7.4 |
| Hoods Closerooftop solar | rooftop solar | 1.7 | under constructionupdated Aug 2023 | Apr 2023 | — | Aug 2023 | Leicester | 7.5 |
| Land Off Ingarsby Lanesolar farm | solar farm | 2.1 | operationalupdated Aug 2016 | May 2015 | granted Jul 2015 | Aug 2016 | Harborough | 8.5 |
| Desford Road, Thurlastonsolar farm | solar farm | 40 | approved, not built may be out of dateupdated Sep 2020 | Mar 2018 | granted Sep 2018 | Sep 2020 | Blaby | 8.6 |
Smaller schemes under 1 MW, mostly rooftop solar (40)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Granby Road Solar PV Panels & Air Source Heat Pumpsrooftop solar | rooftop solar | — | approved, not built may be out of dateupdated Dec 2021 | Dec 2021 | granted Mar 2022 | Dec 2021 | Leicester | 2.3 |
| Madani Schools Federationrooftop solar | rooftop solar | 0.3 | approved, not built may be out of dateupdated May 2024 | Feb 2024 | granted Apr 2024 | May 2024 | Leicester | 2.4 |
| Spire Leicester Hospital, Gartree Roadsolar farm | solar farm | 0.8 | approved, not builtupdated Jul 2025 | Nov 2024 | granted Jun 2025 | Jul 2025 | Oadby and Wigston | 2.4 |
| Harborough Road Storerooftop solar | rooftop solar | 0.2 | operationalupdated Apr 2020 | Dec 2019 | granted Apr 2020 | Apr 2020 | Oadby and Wigston | 2.6 |
| Parklands Leisure Centre, Washbrook Lanerooftop solar | rooftop solar | 0.2 | approved, not builtupdated Jul 2025 | Apr 2025 | granted Jul 2025 | Jul 2025 | Oadby and Wigston | 2.7 |
| Newarke St Car Parksolar farm | solar farm | — | under constructionupdated Jun 2022 | — | granted Nov 2023 | Jun 2022 | Leicester | 2.9 |
| Wigston Swimming Pool, Station Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Nov 2024 | Oct 2024 | granted Nov 2024 | Nov 2024 | Oadby and Wigston | 2.9 |
| St Georges Retail Park, St Georges Wayrooftop solar | rooftop solar | 0.4 | application submitted | Jun 2026 | — | — | Leicester | 3.2 |
| Dysart Way, Birstall Street - Micro Energy Storagebattery storage | battery storage | 0.2 | approved, not builtupdated May 2026 | Feb 2026 | granted Mar 2026 | May 2026 | Leicester | 4.0 |
| Evington Leisure Centrerooftop solar | rooftop solar | — | approved, not builtupdated Apr 2025 | Feb 2025 | granted Mar 2025 | Apr 2025 | Leicester | 4.1 |
| Meridian Leisure Park Solar Photovoltaics Arrayrooftop solar | rooftop solar | 0.2 | application withdrawnupdated Feb 2022 | Jan 2022 | — | Feb 2022 | Blaby | 4.8 |
| Unit F, Meridian Leisure Park, Braunstone Townrooftop solar | rooftop solar | — | approved, not built may be out of dateupdated Jun 2023 | May 2023 | granted Jun 2023 | Jun 2023 | Blaby | 4.8 |
| Showroom Meridian East, Meridian Business Parkrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Feb 2026 | Nov 2025 | granted Jan 2026 | Feb 2026 | Blaby | 4.9 |
| Leicestershire Constabulary, St Johnssolar farm | solar farm | 0.2 | approved, not builtupdated Aug 2024 | Jan 2024 | granted Jul 2024 | Aug 2024 | Blaby | 4.9 |
| National Space Centrerooftop solar | rooftop solar | 0.2 | operationalupdated Mar 2019 | Jan 2019 | granted Mar 2019 | Mar 2019 | Leicester | 5.3 |
| Humberstone Heights Golf Clubrooftop solar | rooftop solar | — | application withdrawnupdated Jan 2022 | Sep 2021 | — | Jan 2022 | Leicester | 5.3 |
| Centurion Way, Braunstone Townrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Dec 2021 | Aug 2021 | granted Oct 2021 | Dec 2021 | Blaby | 5.3 |
| First Bus Depot, Humphreys Wayrooftop solar | rooftop solar | 0.2 | application submitted may be out of dateupdated Mar 2023 | Feb 2023 | — | Mar 2023 | Leicester | 5.4 |
| Enderby Road Industrial Estate, Enderby Roadbattery storage | battery storage | 0.2 | application submittedupdated Mar 2025 | Jan 2025 | — | Mar 2025 | Blaby | 5.7 |
| Dorsey Way, Enderbyrooftop solar | rooftop solar | 0.7 | approved, not builtupdated Apr 2024 | Feb 2024 | granted Apr 2024 | Apr 2024 | Blaby | 5.7 |
| Rushey Mead Academy, Melton Roadrooftop solar | rooftop solar | 0.3 | application submittedupdated Mar 2026 | Jan 2026 | — | Mar 2026 | Leicester | 5.7 |
| Gateway College, Colin Grundy Driverooftop solar | rooftop solar | 0.1 | approved, not builtupdated Dec 2025 | Oct 2025 | granted Nov 2025 | Dec 2025 | Leicester | 5.8 |
| Lewisher Road Solar Arraysrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Sep 2024 | Jun 2024 | granted Sep 2024 | Sep 2024 | Leicester | 5.9 |
| Park View Street - Micro Energy Systembattery storage | battery storage | 0.2 | approved, not builtupdated Jun 2026 | Apr 2026 | granted May 2026 | Jun 2026 | Leicester | 5.9 |
| Langham Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Nov 2023 | Sep 2023 | granted Nov 2023 | Nov 2023 | Leicester | 6.0 |
| The Whittle Estate, Whetstonerooftop solar | rooftop solar | 0.4 | approved, not builtupdated Nov 2021 | Sep 2021 | granted Oct 2021 | Nov 2021 | Blaby | 6.3 |
| Enderby Leisure Centre, Mill Lanebattery storage | battery storage | 0.2 | approved, not builtupdated Apr 2025 | Jan 2025 | granted Mar 2025 | Apr 2025 | Blaby | 6.4 |
| Feldspar Close - Plot N -Solar Panelsrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Aug 2025 | Jun 2025 | granted Aug 2025 | Aug 2025 | Blaby | 6.5 |
| Orchard Mead Academy, Keyham Lane Westrooftop solar | rooftop solar | 0.3 | approved, not builtupdated May 2026 | Jan 2026 | granted Mar 2026 | May 2026 | Leicester | 6.6 |
| Saladworks, Kirby Muxloerooftop solar | rooftop solar | 0.6 | approved, not builtupdated Mar 2025 | Jan 2025 | granted Mar 2025 | Mar 2025 | Blaby | 6.9 |
| Leisure Centre Carlton Park, King Edward Avenuerooftop solar | rooftop solar | — | approved, not builtupdated Sep 2025 | Jul 2025 | granted Sep 2025 | Sep 2025 | Blaby | 6.9 |
| Bingo Club, Beaumont Wayrooftop solar | rooftop solar | 0.4 | approved, not builtupdated Sep 2023 | Jul 2023 | granted Sep 2023 | Sep 2023 | Leicester | 7.4 |
| Forest Roadbattery storage | battery storage | — | application submittedupdated Nov 2024 | Sep 2024 | — | Nov 2024 | Blaby | 7.4 |
| Lodge Farm Solar Farm & Battery Storagesolar farm | solar farm | — | application submitted may be out of dateupdated Aug 2025 | May 2022 | — | Aug 2025 | Harborough | 7.7 |
| Lodge Farm Solar Farm & Battery Storagebattery storage | battery storage | — | approved, not builtupdated Feb 2026 | May 2022 | granted Mar 2024 | Feb 2026 | Harborough | 7.7 |
| Ashton Business Park, Ashton Closerooftop solar | rooftop solar | 0.2 | approved, not builtupdated Aug 2024 | Jun 2024 | granted Aug 2024 | Aug 2024 | Leicester | 7.7 |
| Gynsill Lane, Leicester Road - Micro Energy Storagebattery storage | battery storage | 0.2 | approved, not built | Mar 2026 | granted May 2026 | — | Charnwood | 7.8 |
| Roman Avenue, Unit Arooftop solar | rooftop solar | 0.8 | approved, not builtupdated Mar 2024 | Jan 2024 | granted Mar 2024 | Mar 2024 | Blaby | 7.8 |
| Kirby Road Solar Panelsrooftop solar | rooftop solar | 0.5 | under constructionupdated Jan 2022 | Nov 2020 | granted Feb 2021 | Jan 2022 | Blaby | 8.0 |
| Fiona Cairns HQrooftop solar | rooftop solar | — | no application requiredupdated May 2023 | — | — | May 2023 | Harborough | 10.0 |
Distance from the average position of the LE2 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 8 | 1 | 5 | 2 | 0 | 91 |
| Rooftop solar | 33 | 3 | 25 | 2 | 0 | 15.1 |
| Battery storage | 10 | 2 | 5 | 3 | 0 | 1 |
MW in pipeline: pending, approved and under-construction capacity.
How Leicester decides solar, wind and battery applications
| Applications | Leicester | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 15 | 10,236 |
| Refused | 0 (0%) | 19% |
| Solar refused | 0 of 13 | 12% |
| Battery storage refused | 0 of 2 | 16% |
| Median time from submission to decision | 7.9 weeks | 17.0 weeks |
| Appeals lodged / allowed | 0 / 0 | — |
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near LE2, 6 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.