Energy Projects Near You

Desford Road, Thurlaston (40 MW solar farm)

Desford Road, Thurlaston is a 40 MW solar farm project in Blaby, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 17 September 2018, not yet built; the record was last updated on 2 September 2020. REPD also records that the planning permission expired on 17 September 2021, so the project may not go ahead in this form. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

40 MWsolar farm
approved, not builtmay be out of datestatus in REPD
2 September 2020record last updated
Blabycouncil area

REPD also records that the planning permission expired on 17 September 2021, so the project may not go ahead in this form.

Planning timeline

DateStage
27 March 2018Application submitted
17 September 2018Planning permission granted
17 September 2021Permission expired

Project details

Technology
solar farm
Capacity
40 MW
Status (REPD)
approved, not built
Record last updated
2 September 2020
Operator or applicant
Elgin Energy EsCo
Planning authority
Blaby
Planning application reference
18/0242/FUL
Site area
80.2 ha
Address (REPD)
Field No 8236, Hinckley Road, Land To South And West Of, Desford Road, Thurlaston, Leicester
Council area (by location)
Blaby
Time to decision
25 weeks
REPD reference
6515

Who decides

ApplicationsBlabyUK
Decided applications (solar, wind, battery)2210,236
Refused0 (0%)19%
Solar refused0 of 1712%
Battery storage refused0 of 516%
Median time from submission to decision8.4 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Enderby Storage, Redcomb Farmbattery storage49.9operational1.6
National Grid Enderby Substationbattery storage57operational2.0
Hill Farm Solar Parksolar farm20application submitted2.4
Normanton Energy Reservebattery storage500approved, not built2.5
Hinckley Road Solar Farmsolar farm40approved, not built3.5
Desford Solar Farmsolar farm5operational4.2
Lindridge Farmsolar farm5operational6.3
Kirkby Roadsolar farm23.5approved, not built7.2
Hall Farm Solar Farm (Newbold Verdon)solar farm5operational7.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.6036, -1.2444).