Desford Solar Farm (5 MW)

Desford Solar Farm is a 5 MW solar farm project in Hinckley and Bosworth, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 23 March 2016; the record was last updated on 28 November 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
28 November 2016record last updated
Hinckley and Bosworthcouncil area

Planning timeline

DateStage
7 July 2014Application submitted
10 December 2014Planning permission granted
15 November 2015Construction started
23 March 2016Operational

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
28 November 2016
Operator or applicant
Trina Solar
Planning authority
Hinckley and Bosworth
Planning application reference
14/00654/FUL
Site area
9.7 ha
Address (REPD)
Land Adjacent Charnwood Poultry Farm Desford Road Desford Leicester Leicestershire
Council area (by location)
Hinckley and Bosworth
Time to decision
22 weeks
REPD reference
1885

Who decides

ApplicationsHinckley and BosworthUK
Decided applications (solar, wind, battery)3010,236
Refused2 (7%)19%
Solar refused2 of 2612%
Onshore wind refused0 of 345%
Battery storage refused0 of 116%
Median time from submission to decision13.1 weeks17.0 weeks
Appeals lodged / allowed1 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Lindridge Farmsolar farm5operational3.6
Desford Road, Thurlastonsolar farm40approved, not built4.2
Heath Road, Bagworth Solar Farmsolar farm21.5application submitted5.0
Enderby Storage, Redcomb Farmbattery storage49.9operational5.3
National Grid Enderby Substationbattery storage57operational5.4
Hill Farm Solar Parksolar farm20application submitted5.6
Hinckley Road Solar Farmsolar farm40approved, not built5.8
Normanton Energy Reservebattery storage500approved, not built5.9
Hall Farm Solar Farm (Newbold Verdon)solar farm5operational6.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.64, -1.2586).