Solar, wind and battery projects near Leicester (LE19)
50 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of LE19 (Blaby): 6 are waiting for a planning decision, 33 approved but not yet running, 10 operational. The largest live scheme is Normanton Energy Reserve (500 MW battery storage, approved on 16 January 2024, not yet built), 4.2 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of LE19
Projects of 1 MW and more (17)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Dorsey Way, Enderbyrooftop solar | rooftop solar | 1.8 | approved, not builtupdated Apr 2024 | Feb 2024 | granted Apr 2024 | Apr 2024 | Blaby | 1.3 |
| National Grid Enderby Substationbattery storage | battery storage | 57 | operationalupdated Mar 2026 | Aug 2020 | granted Feb 2021 | Mar 2026 | Blaby | 1.6 |
| Enderby Storage, Redcomb Farmbattery storage | battery storage | 49.9 | operationalupdated Mar 2026 | Oct 2017 | granted Jan 2018 | Mar 2026 | Blaby | 1.6 |
| Desford Road, Thurlastonsolar farm | solar farm | 40 | approved, not built may be out of dateupdated Sep 2020 | Mar 2018 | granted Sep 2018 | Sep 2020 | Blaby | 3.2 |
| Land at and adjacent to Leicester Forest Servicesbattery storage | battery storage | 1.5 | operationalupdated Mar 2020 | Jun 2017 | granted Feb 2022 | Mar 2020 | Blaby | 3.7 |
| Normanton Energy Reservebattery storage | battery storage | 500 | approved, not builtupdated Apr 2025 | Dec 2022 | granted Jan 2024 | Apr 2025 | Blaby | 4.2 |
| Hill Farm Solar Parksolar farm | solar farm | 20 | application submitted may be out of dateupdated Dec 2021 | Nov 2021 | — | Dec 2021 | Blaby | 4.4 |
| Sunningdale Roadrooftop solar | rooftop solar | 1.6 | approved, not builtupdated Aug 2025 | Jun 2025 | granted Aug 2025 | Aug 2025 | Leicester | 5.0 |
| Hinckley Road Solar Farmsolar farm | solar farm | 40 | approved, not builtupdated Apr 2026 | Feb 2022 | granted May 2023 | Apr 2026 | Blaby | 5.7 |
| Blaby Solar Farmsolar farm | solar farm | 3.5 | operationalupdated Jul 2016 | Aug 2015 | granted Nov 2015 | Jul 2016 | Blaby | 5.7 |
| Desford Solar Farmsolar farm | solar farm | 5 | operationalupdated Nov 2016 | Jul 2014 | granted Dec 2014 | Nov 2016 | Hinckley and Bosworth | 6.9 |
| Soars Lodge Farm, Foston Lane Solar Farmsolar farm | solar farm | 49.9 | approved, not builtupdated May 2026 | Oct 2024 | granted Mar 2026 | May 2026 | Blaby | 7.8 |
| Kirkby Roadsolar farm | solar farm | 23.5 | approved, not built may be out of dateupdated Oct 2024 | Dec 2019 | granted Oct 2022 | Oct 2024 | Hinckley and Bosworth | 9.3 |
| Lindridge Farmsolar farm | solar farm | 5 | operationalupdated Dec 2015 | Feb 2015 | granted Apr 2015 | Dec 2015 | Hinckley and Bosworth | 9.4 |
| Low Spinney Wind Farmwind farm | wind farm | 8 | operationalupdated May 2012 | Feb 2009 | granted Sep 2009 | May 2012 | Harborough | 9.5 |
| Pepsico International Limited, Leycroft Roadrooftop solar | rooftop solar | 3.2 | under constructionupdated Mar 2026 | Jan 2024 | granted Mar 2024 | Mar 2026 | Leicester | 9.8 |
| Halifax Farmwind turbine | wind turbine | 1.6 | operationalupdated Oct 2016 | Jun 2014 | granted Sep 2014 | Oct 2016 | Hinckley and Bosworth | 9.9 |
Smaller schemes under 1 MW, mostly rooftop solar (33)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Enderby Leisure Centre, Mill Lanebattery storage | battery storage | 0.2 | approved, not builtupdated Apr 2025 | Jan 2025 | granted Mar 2025 | Apr 2025 | Blaby | 0.2 |
| Leisure Centre Carlton Park, King Edward Avenuerooftop solar | rooftop solar | — | approved, not builtupdated Sep 2025 | Jul 2025 | granted Sep 2025 | Sep 2025 | Blaby | 0.8 |
| Feldspar Close - Plot N -Solar Panelsrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Aug 2025 | Jun 2025 | granted Aug 2025 | Aug 2025 | Blaby | 1.2 |
| Dorsey Way, Enderbyrooftop solar | rooftop solar | 0.7 | approved, not builtupdated Apr 2024 | Feb 2024 | granted Apr 2024 | Apr 2024 | Blaby | 1.3 |
| Leicestershire Constabulary, St Johnssolar farm | solar farm | 0.2 | approved, not builtupdated Aug 2024 | Jan 2024 | granted Jul 2024 | Aug 2024 | Blaby | 1.7 |
| Forest Roadbattery storage | battery storage | — | application submittedupdated Nov 2024 | Sep 2024 | — | Nov 2024 | Blaby | 1.7 |
| Enderby Road Industrial Estate, Enderby Roadbattery storage | battery storage | 0.2 | application submittedupdated Mar 2025 | Jan 2025 | — | Mar 2025 | Blaby | 1.9 |
| Showroom Meridian East, Meridian Business Parkrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Feb 2026 | Nov 2025 | granted Jan 2026 | Feb 2026 | Blaby | 2.3 |
| Centurion Way, Braunstone Townrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Dec 2021 | Aug 2021 | granted Oct 2021 | Dec 2021 | Blaby | 2.7 |
| The Whittle Estate, Whetstonerooftop solar | rooftop solar | 0.4 | approved, not builtupdated Nov 2021 | Sep 2021 | granted Oct 2021 | Nov 2021 | Blaby | 2.9 |
| Unit F, Meridian Leisure Park, Braunstone Townrooftop solar | rooftop solar | — | approved, not built may be out of dateupdated Jun 2023 | May 2023 | granted Jun 2023 | Jun 2023 | Blaby | 3.4 |
| Meridian Leisure Park Solar Photovoltaics Arrayrooftop solar | rooftop solar | 0.2 | application withdrawnupdated Feb 2022 | Jan 2022 | — | Feb 2022 | Blaby | 3.4 |
| Granby Road Solar PV Panels & Air Source Heat Pumpsrooftop solar | rooftop solar | — | approved, not built may be out of dateupdated Dec 2021 | Dec 2021 | granted Mar 2022 | Dec 2021 | Leicester | 4.5 |
| Saladworks, Kirby Muxloerooftop solar | rooftop solar | 0.6 | approved, not builtupdated Mar 2025 | Jan 2025 | granted Mar 2025 | Mar 2025 | Blaby | 4.9 |
| Park House Farm, Leicester Lanewind farm | wind farm | 0.8 | approved, not builtupdated Jun 2026 | Oct 2025 | granted Jun 2026 | Jun 2026 | Hinckley and Bosworth | 5.6 |
| Park View Street - Micro Energy Systembattery storage | battery storage | 0.2 | approved, not builtupdated Jun 2026 | Apr 2026 | granted May 2026 | Jun 2026 | Leicester | 5.8 |
| Austral House, Coventry Roadrooftop solar | rooftop solar | 0.1 | approved, not builtupdated Jan 2023 | Nov 2022 | granted Jan 2023 | Jan 2023 | Harborough | 5.9 |
| Wigston Swimming Pool, Station Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Nov 2024 | Oct 2024 | granted Nov 2024 | Nov 2024 | Oadby and Wigston | 6.1 |
| Roman Avenue, Unit Arooftop solar | rooftop solar | 0.8 | approved, not builtupdated Mar 2024 | Jan 2024 | granted Mar 2024 | Mar 2024 | Blaby | 6.2 |
| Kirby Road Solar Panelsrooftop solar | rooftop solar | 0.5 | under constructionupdated Jan 2022 | Nov 2020 | granted Feb 2021 | Jan 2022 | Blaby | 6.8 |
| Newarke St Car Parksolar farm | solar farm | — | under constructionupdated Jun 2022 | — | granted Nov 2023 | Jun 2022 | Leicester | 7.0 |
| St Georges Retail Park, St Georges Wayrooftop solar | rooftop solar | 0.4 | application submitted | Jun 2026 | — | — | Leicester | 8.1 |
| Parklands Leisure Centre, Washbrook Lanerooftop solar | rooftop solar | 0.2 | approved, not builtupdated Jul 2025 | Apr 2025 | granted Jul 2025 | Jul 2025 | Oadby and Wigston | 8.1 |
| Old Station Yard, Station Roadsolar farm | solar farm | 0.3 | application submitted may be out of dateupdated Jul 2024 | Jun 2024 | — | Jul 2024 | Harborough | 8.4 |
| Heath Lane Academy, Heath Lanerooftop solar | rooftop solar | 0.3 | approved, not builtupdated Jul 2026 | Apr 2026 | granted Jun 2026 | Jul 2026 | Hinckley and Bosworth | 8.4 |
| Madani Schools Federationrooftop solar | rooftop solar | 0.3 | approved, not built may be out of dateupdated May 2024 | Feb 2024 | granted Apr 2024 | May 2024 | Leicester | 8.5 |
| Dysart Way, Birstall Street - Micro Energy Storagebattery storage | battery storage | 0.2 | approved, not builtupdated May 2026 | Feb 2026 | granted Mar 2026 | May 2026 | Leicester | 8.7 |
| Harborough Road Storerooftop solar | rooftop solar | 0.2 | operationalupdated Apr 2020 | Dec 2019 | granted Apr 2020 | Apr 2020 | Oadby and Wigston | 8.7 |
| First Bus Depot, Humphreys Wayrooftop solar | rooftop solar | 0.2 | application submitted may be out of dateupdated Mar 2023 | Feb 2023 | — | Mar 2023 | Leicester | 8.9 |
| Spire Leicester Hospital, Gartree Roadsolar farm | solar farm | 0.8 | approved, not builtupdated Jul 2025 | Nov 2024 | granted Jun 2025 | Jul 2025 | Oadby and Wigston | 9.0 |
| National Space Centrerooftop solar | rooftop solar | 0.2 | operationalupdated Mar 2019 | Jan 2019 | granted Mar 2019 | Mar 2019 | Leicester | 9.1 |
| Gynsill Lane, Leicester Road - Micro Energy Storagebattery storage | battery storage | 0.2 | approved, not built | Mar 2026 | granted May 2026 | — | Charnwood | 9.1 |
| Bingo Club, Beaumont Wayrooftop solar | rooftop solar | 0.4 | approved, not builtupdated Sep 2023 | Jul 2023 | granted Sep 2023 | Sep 2023 | Leicester | 9.3 |
Distance from the average position of the LE19 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 12 | 2 | 7 | 3 | 0 | 175 |
| Rooftop solar | 25 | 2 | 20 | 2 | 0 | 12.6 |
| Wind farm | 2 | 0 | 1 | 1 | 0 | 0.8 |
| Wind turbine | 1 | 0 | 0 | 1 | 0 | 0 |
| Battery storage | 10 | 2 | 5 | 3 | 0 | 501 |
MW in pipeline: pending, approved and under-construction capacity.
How Blaby decides solar, wind and battery applications
| Applications | Blaby | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 22 | 10,236 |
| Refused | 0 (0%) | 19% |
| Solar refused | 0 of 17 | 12% |
| Battery storage refused | 0 of 5 | 16% |
| Median time from submission to decision | 8.4 weeks | 17.0 weeks |
| Appeals lodged / allowed | 0 / 0 | — |
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near LE19, 8 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.