Normanton Energy Reserve (500 MW battery storage)

Normanton Energy Reserve is a 500 MW battery storage project in Blaby, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 16 January 2024, not yet built; the record was last updated on 1 April 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

500 MWbattery storage
approved, not builtstatus in REPD
1 April 2025record last updated
Blabycouncil area

Planning timeline

DateStage
13 December 2022Application submitted
16 January 2024Planning permission granted
16 January 2027Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
500 MW
Status (REPD)
approved, not built
Record last updated
1 April 2025
Operator or applicant
Exagen SPVO2 Limited
Planning authority
Blaby
Planning application reference
22/1204/FUL
Address (REPD)
NW/O Earl Shilton Road Thurlaston
Council area (by location)
Blaby
Time to decision
57 weeks
Name in REPD
Normanton Energy Reserve - Battery Storage
REPD reference
11988

Who decides

ApplicationsBlabyUK
Decided applications (solar, wind, battery)2210,236
Refused0 (0%)19%
Solar refused0 of 1712%
Battery storage refused0 of 516%
Median time from submission to decision8.4 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Hill Farm Solar Parksolar farm20application submitted0.3
Hinckley Road Solar Farmsolar farm40approved, not built1.5
Desford Road, Thurlastonsolar farm40approved, not built2.5
Enderby Storage, Redcomb Farmbattery storage49.9operational3.3
National Grid Enderby Substationbattery storage57operational3.9
Kirkby Roadsolar farm23.5approved, not built5.1
Desford Solar Farmsolar farm5operational5.9
Lindridge Farmsolar farm5operational6.8
Hangmans Hall Farmsolar farm35refused7.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.5876, -1.2697).