Hinckley Road Solar Farm (40 MW)

Hinckley Road Solar Farm is a 40 MW solar farm project in Blaby, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 10 May 2023, not yet built; the record was last updated on 8 April 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

40 MWsolar farm
approved, not builtstatus in REPD
8 April 2026record last updated
Blabycouncil area

Planning timeline

DateStage
9 February 2022Application submitted
10 May 2023Planning permission granted

Project details

Technology
solar farm
Capacity
40 MW
Status (REPD)
approved, not built
Record last updated
8 April 2026
Operator or applicant
Capital Dynamics Limited
Planning authority
Blaby
Planning application reference
21/01242/FUL
Site area
60.2 ha
Address (REPD)
Clump Farm Peckleton Hinckley Road, Leicester Road
Council area (by location)
Blaby
Time to decision
65 weeks
Contracts for Difference
AR6
Name in REPD
Hinckley Road - Solar Farm
REPD reference
7715

Who decides

ApplicationsBlabyUK
Decided applications (solar, wind, battery)2210,236
Refused0 (0%)19%
Solar refused0 of 1712%
Battery storage refused0 of 516%
Median time from submission to decision8.4 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Hill Farm Solar Parksolar farm20application submitted1.3
Normanton Energy Reservebattery storage500approved, not built1.5
Desford Road, Thurlastonsolar farm40approved, not built3.5
Kirkby Roadsolar farm23.5approved, not built3.7
Enderby Storage, Redcomb Farmbattery storage49.9operational4.7
National Grid Enderby Substationbattery storage57operational5.2
Hangmans Hall Farmsolar farm35refused5.6
Hall Farm Solar Farm (Newbold Verdon)solar farm5operational5.8
Desford Solar Farmsolar farm5operational5.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.5913, -1.2915).