Solar, wind and battery projects near Hinckley (LE10)
30 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of LE10 (Hinckley and Bosworth): 4 are waiting for a planning decision, 22 approved but not yet running, 3 operational. The largest live scheme is Normanton Energy Reserve (500 MW battery storage, approved on 16 January 2024, not yet built), 8.8 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of LE10
Projects of 1 MW and more (14)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Elms Farm - Hinckley Solar Farm & Battery Storagesolar farm | solar farm | 49.9 | approved, not built may be out of dateupdated Mar 2024 | Jun 2021 | granted Nov 2022 | Mar 2024 | Rugby | 2.3 |
| Triumph Motorcycles, Normandy Waysolar farm | solar farm | 1.3 | approved, not builtupdated Nov 2023 | Aug 2023 | granted Nov 2023 | Nov 2023 | Hinckley and Bosworth | 2.6 |
| Lychgate Lane, Aston Flamville Solar Farmsolar farm | solar farm | 20 | under constructionupdated Jul 2026 | Aug 2022 | granted Apr 2024 | Jul 2026 | Blaby | 3.3 |
| Basin Bridge Farmsolar farm | solar farm | 5 | operationalupdated Dec 2016 | Sep 2015 | granted Feb 2016 | Dec 2016 | Hinckley and Bosworth | 4.3 |
| The Stablessolar | solar | 1.8 | operationalupdated Dec 2014 | Oct 2012 | granted Apr 2014 | Dec 2014 | Hinckley and Bosworth | 5.1 |
| Kirkby Roadsolar farm | solar farm | 23.5 | approved, not built may be out of dateupdated Oct 2024 | Dec 2019 | granted Oct 2022 | Oct 2024 | Hinckley and Bosworth | 5.4 |
| Hangmans Hall Farmsolar farm | solar farm | 35 | refusedupdated Sep 2020 | Nov 2019 | refused Jul 2020 | Sep 2020 | Hinckley and Bosworth | 6.0 |
| Weddington Roadbattery storage | battery storage | 49.9 | approved, not builtupdated Jul 2026 | Aug 2024 | granted Feb 2026 | Jul 2026 | Nuneaton and Bedworth | 6.4 |
| Horiba Mira, Mira Drivesolar farm | solar farm | 7 | operationalupdated May 2026 | Sep 2022 | granted Feb 2023 | May 2026 | Hinckley and Bosworth | 6.4 |
| Coal Pit Lane, Willey Solar Farmsolar farm | solar farm | 16 | application submittedupdated Sep 2025 | Jul 2025 | — | Sep 2025 | Rugby | 8.0 |
| Hinckley Road Solar Farmsolar farm | solar farm | 40 | approved, not builtupdated Apr 2026 | Feb 2022 | granted May 2023 | Apr 2026 | Blaby | 8.1 |
| Normanton Energy Reservebattery storage | battery storage | 500 | approved, not builtupdated Apr 2025 | Dec 2022 | granted Jan 2024 | Apr 2025 | Blaby | 8.8 |
| Hill Farm Solar Parksolar farm | solar farm | 20 | application submitted may be out of dateupdated Dec 2021 | Nov 2021 | — | Dec 2021 | Blaby | 8.9 |
| Hollyhurst Farm, Mile Tree Lanesolar farm | solar farm | 25.6 | application submittedupdated Mar 2025 | Dec 2024 | — | Mar 2025 | Nuneaton and Bedworth | 9.4 |
Smaller schemes under 1 MW, mostly rooftop solar (16)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Hinckley Leisure Centre, Argents Meadrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Oct 2024 | Aug 2024 | granted Aug 2024 | Oct 2024 | Hinckley and Bosworth | 0.4 |
| Dpd International Gateway, Logix Road Phase 1rooftop solar | rooftop solar | 0.8 | approved, not builtupdated Oct 2023 | Aug 2023 | granted Oct 2023 | Oct 2023 | Hinckley and Bosworth | 1.3 |
| DPD International Gateway, Logix Road - Phase 2, Solar Panelsrooftop solar | rooftop solar | 0.5 | approved, not builtupdated Apr 2024 | Feb 2024 | granted Apr 2024 | Apr 2024 | Hinckley and Bosworth | 1.7 |
| E M E B Sports & Social Club, Nutts Lanesolar farm | solar farm | 0.3 | approved, not builtupdated Nov 2023 | May 2023 | granted Nov 2023 | Nov 2023 | Hinckley and Bosworth | 1.8 |
| Morrison Supermarkets, Cloverfieldrooftop solar | rooftop solar | 0.4 | approved, not builtupdated Nov 2022 | Oct 2022 | granted Nov 2022 | Nov 2022 | Hinckley and Bosworth | 2.1 |
| Elms Farm Solar Farm & Battery Storagebattery storage | battery storage | — | approved, not built may be out of dateupdated Mar 2024 | Jun 2021 | granted Nov 2022 | Mar 2024 | Rugby | 2.3 |
| Hydes Lane, Stretton Baskervillebattery storage | battery storage | — | approved, not builtupdated Aug 2024 | Feb 2023 | granted Jul 2024 | Aug 2024 | Rugby | 2.7 |
| Tesco Distribution Depot, Dodwells Roadrooftop solar | rooftop solar | — | approved, not builtupdated Oct 2024 | Aug 2024 | granted Sep 2024 | Oct 2024 | Hinckley and Bosworth | 2.8 |
| Burbage Houserooftop solar | rooftop solar | 0.3 | approved, not built may be out of dateupdated Aug 2023 | Apr 2023 | granted Jul 2023 | Aug 2023 | Hinckley and Bosworth | 3.2 |
| Heath Lane Academy, Heath Lanerooftop solar | rooftop solar | 0.3 | approved, not builtupdated Jul 2026 | Apr 2026 | granted Jun 2026 | Jul 2026 | Hinckley and Bosworth | 5.0 |
| North Warwickshire College, Hinckley Roadrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Nov 2023 | Jul 2023 | granted Sep 2023 | Nov 2023 | Nuneaton and Bedworth | 5.4 |
| George eliot high school, Raveloe Driverooftop solar | rooftop solar | 0.3 | approved, not builtupdated Mar 2026 | Oct 2025 | granted Dec 2025 | Mar 2026 | Nuneaton and Bedworth | 6.8 |
| St Georges Way Solar photovoltaicsrooftop solar | rooftop solar | 0.6 | approved, not builtupdated Apr 2022 | Mar 2022 | granted May 2022 | Apr 2022 | Nuneaton and Bedworth | 7.9 |
| Austral House, Coventry Roadrooftop solar | rooftop solar | 0.1 | approved, not builtupdated Jan 2023 | Nov 2022 | granted Jan 2023 | Jan 2023 | Harborough | 8.0 |
| Hamilton Way, Unit 12rooftop solar | rooftop solar | 0.7 | approved, not builtupdated Jun 2023 | Mar 2023 | granted Apr 2023 | Jun 2023 | Nuneaton and Bedworth | 8.3 |
| The Nuneaton Academy, Radnor Driverooftop solar | rooftop solar | 0.5 | application submittedupdated May 2026 | Mar 2026 | — | May 2026 | Nuneaton and Bedworth | 9.1 |
Distance from the average position of the LE10 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 12 | 3 | 6 | 2 | 1 | 197 |
| Rooftop solar | 13 | 1 | 12 | 0 | 0 | 5.1 |
| Solar | 1 | 0 | 0 | 1 | 0 | 0 |
| Battery storage | 4 | 0 | 4 | 0 | 0 | 550 |
MW in pipeline: pending, approved and under-construction capacity.
How Hinckley and Bosworth decides solar, wind and battery applications
| Applications | Hinckley and Bosworth | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 30 | 10,236 |
| Refused | 2 (7%) | 19% |
| Solar refused | 2 of 26 | 12% |
| Onshore wind refused | 0 of 3 | 45% |
| Battery storage refused | 0 of 1 | 16% |
| Median time from submission to decision | 13.1 weeks | 17.0 weeks |
| Appeals lodged / allowed | 1 / 1 | — |
All projects in Hinckley and Bosworth
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near LE10, 5 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.