Lychgate Lane, Aston Flamville Solar Farm (20 MW)

Lychgate Lane, Aston Flamville Solar Farm is a 20 MW solar farm project in Blaby, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: under construction since 1 June 2026; the record was last updated on 13 July 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

20 MWsolar farm
under constructionstatus in REPD
13 July 2026record last updated
Blabycouncil area

Planning timeline

DateStage
4 August 2022Application submitted
11 April 2024Planning permission granted
1 June 2026Construction started

Project details

Technology
solar farm
Capacity
20 MW
Status (REPD)
under construction
Record last updated
13 July 2026
Operator or applicant
Elgin Energy ES Co Limited
Planning authority
Blaby
Planning application reference
22/0048/FUL
Site area
41.8 ha
Address (REPD)
North And South Of Lychgate Lane Aston Flamville
Council area (by location)
Blaby
Time to decision
88 weeks
Contracts for Difference
AR6
Name in REPD
Lychgate Lane, Aston Flamville - Solar Farm
REPD reference
11885

Who decides

ApplicationsBlabyUK
Decided applications (solar, wind, battery)2210,236
Refused0 (0%)19%
Solar refused0 of 1712%
Battery storage refused0 of 516%
Median time from submission to decision8.4 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Elms Farm - Hinckley Solar Farm & Battery Storagesolar farm49.9approved, not built5.0
Coal Pit Lane, Willey Solar Farmsolar farm16application submitted6.2
Kirkby Roadsolar farm23.5approved, not built6.3
Hinckley Road Solar Farmsolar farm40approved, not built7.4
Basin Bridge Farmsolar farm5operational7.4
Normanton Energy Reservebattery storage500approved, not built7.5
Hill Farm Solar Parksolar farm20application submitted7.7
Hangmans Hall Farmsolar farm35refused7.8
Weddington Roadbattery storage49.9approved, not built9.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.528, -1.3232).