Energy Projects Near You

Elms Farm - Hinckley Solar Farm & Battery Storage (49.9 MW)

Elms Farm - Hinckley Solar Farm & Battery Storage is a 49.9 MW solar farm project in Rugby, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 22 November 2022, not yet built; the record was last updated on 12 March 2024. REPD records the planning permission as expiring on 22 November 2025, but the project holds a Contracts for Difference award (AR5), so construction may have started. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWsolar farm
approved, not builtmay be out of datestatus in REPD
12 March 2024record last updated
Rugbycouncil area

REPD records the planning permission as expiring on 22 November 2025, but the project holds a Contracts for Difference award (AR5), so construction may have started.

Planning timeline

DateStage
7 June 2021Application submitted
22 November 2022Planning permission granted
22 November 2025Permission expired

Project details

Technology
solar farm
Capacity
49.9 MW
Status (REPD)
approved, not built
Record last updated
12 March 2024
Operator or applicant
Low Carbon UK Solar Investment Co Limited
Planning authority
Rugby
Planning application reference
R21/0622
Site area
84.5 ha
Address (REPD)
Elms Farm, Watling Street, Hinckley
Council area (by location)
Rugby
Time to decision
76 weeks
Contracts for Difference
AR5
REPD reference
8508

The scheme also includes 49.9 MW of solar farm, recorded separately in REPD (approved, not built).

Who decides

ApplicationsRugbyUK
Decided applications (solar, wind, battery)2510,236
Refused3 (12%)19%
Solar refused1 of 1812%
Onshore wind refused2 of 245%
Battery storage refused0 of 516%
Median time from submission to decision12.6 weeks17.0 weeks
Appeals lodged / allowed1 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Basin Bridge Farmsolar farm5operational4.3
Weddington Roadbattery storage49.9approved, not built4.5
Lychgate Lane, Aston Flamville Solar Farmsolar farm20under construction5.0
Horiba Mira, Mira Drivesolar farm7operational5.4
Hollyhurst Farm, Mile Tree Lanesolar farm25.6application submitted7.3
Kirkby Roadsolar farm23.5approved, not built7.4
Hangmans Hall Farmsolar farm35refused7.5
Coal Pit Lane, Willey Solar Farmsolar farm16application submitted7.9
Tolldish Hall Farm, Parrotts Grovesolar farm25under construction8.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.5249, -1.3976).