Solar, wind and battery projects near Leicester (LE9)
55 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of LE9 (Hinckley and Bosworth): 5 are waiting for a planning decision, 36 approved but not yet running, 10 operational. The largest live scheme is Normanton Energy Reserve (500 MW battery storage, approved on 16 January 2024, not yet built), 1.8 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of LE9
Projects of 1 MW and more (24)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Normanton Energy Reservebattery storage | battery storage | 500 | approved, not builtupdated Apr 2025 | Dec 2022 | granted Jan 2024 | Apr 2025 | Blaby | 1.8 |
| Hill Farm Solar Parksolar farm | solar farm | 20 | application submitted may be out of dateupdated Dec 2021 | Nov 2021 | — | Dec 2021 | Blaby | 2.0 |
| Hinckley Road Solar Farmsolar farm | solar farm | 40 | approved, not builtupdated Apr 2026 | Feb 2022 | granted May 2023 | Apr 2026 | Blaby | 2.1 |
| Desford Road, Thurlastonsolar farm | solar farm | 40 | approved, not built may be out of dateupdated Sep 2020 | Mar 2018 | granted Sep 2018 | Sep 2020 | Blaby | 4.2 |
| Kirkby Roadsolar farm | solar farm | 23.5 | approved, not built may be out of dateupdated Oct 2024 | Dec 2019 | granted Oct 2022 | Oct 2024 | Hinckley and Bosworth | 4.4 |
| Enderby Storage, Redcomb Farmbattery storage | battery storage | 49.9 | operationalupdated Mar 2026 | Oct 2017 | granted Jan 2018 | Mar 2026 | Blaby | 4.8 |
| National Grid Enderby Substationbattery storage | battery storage | 57 | operationalupdated Mar 2026 | Aug 2020 | granted Feb 2021 | Mar 2026 | Blaby | 5.3 |
| Lychgate Lane, Aston Flamville Solar Farmsolar farm | solar farm | 20 | under constructionupdated Jul 2026 | Aug 2022 | granted Apr 2024 | Jul 2026 | Blaby | 5.8 |
| Dorsey Way, Enderbyrooftop solar | rooftop solar | 1.8 | approved, not builtupdated Apr 2024 | Feb 2024 | granted Apr 2024 | Apr 2024 | Blaby | 6.1 |
| Hangmans Hall Farmsolar farm | solar farm | 35 | refusedupdated Sep 2020 | Nov 2019 | refused Jul 2020 | Sep 2020 | Hinckley and Bosworth | 6.6 |
| Land at and adjacent to Leicester Forest Servicesbattery storage | battery storage | 1.5 | operationalupdated Mar 2020 | Jun 2017 | granted Feb 2022 | Mar 2020 | Blaby | 7.2 |
| Desford Solar Farmsolar farm | solar farm | 5 | operationalupdated Nov 2016 | Jul 2014 | granted Dec 2014 | Nov 2016 | Hinckley and Bosworth | 7.6 |
| Hall Farm Solar Farm (Newbold Verdon)solar farm | solar farm | 5 | operationalupdated Jul 2016 | Jul 2014 | granted Jun 2015 | Jul 2016 | Hinckley and Bosworth | 7.8 |
| Halifax Farmwind turbine | wind turbine | 1.6 | operationalupdated Oct 2016 | Jun 2014 | granted Sep 2014 | Oct 2016 | Hinckley and Bosworth | 7.9 |
| Lindridge Farmsolar farm | solar farm | 5 | operationalupdated Dec 2015 | Feb 2015 | granted Apr 2015 | Dec 2015 | Hinckley and Bosworth | 8.0 |
| Sunningdale Roadrooftop solar | rooftop solar | 1.6 | approved, not builtupdated Aug 2025 | Jun 2025 | granted Aug 2025 | Aug 2025 | Leicester | 8.3 |
| The Stablessolar | solar | 1.8 | operationalupdated Dec 2014 | Oct 2012 | granted Apr 2014 | Dec 2014 | Hinckley and Bosworth | 8.5 |
| Land North East Of Heath Farmsolar farm | solar farm | 2.8 | application withdrawnupdated May 2015 | Jan 2015 | — | May 2015 | Hinckley and Bosworth | 8.7 |
| Heath Road, Bagworth Solar Farmsolar farm | solar farm | 21.5 | application submittedupdated Sep 2025 | Jul 2025 | — | Sep 2025 | Hinckley and Bosworth | 9.0 |
| Triumph Motorcycles, Normandy Waysolar farm | solar farm | 1.3 | approved, not builtupdated Nov 2023 | Aug 2023 | granted Nov 2023 | Nov 2023 | Hinckley and Bosworth | 9.1 |
| Basin Bridge Farmsolar farm | solar farm | 5 | operationalupdated Dec 2016 | Sep 2015 | granted Feb 2016 | Dec 2016 | Hinckley and Bosworth | 9.3 |
| Stonehaven Wind Turbinewind turbine | wind turbine | 1.5 | abandonedupdated Feb 2016 | Apr 2014 | granted Jul 2014 | Feb 2016 | Hinckley and Bosworth | 9.4 |
| Desford Brick Works, Bagworthrooftop solar | rooftop solar | 2.6 | operationalupdated Mar 2024 | May 2022 | granted Jul 2022 | Mar 2024 | Hinckley and Bosworth | 9.4 |
| Elms Farm - Hinckley Solar Farm & Battery Storagesolar farm | solar farm | 49.9 | approved, not built may be out of dateupdated Mar 2024 | Jun 2021 | granted Nov 2022 | Mar 2024 | Rugby | 9.5 |
Smaller schemes under 1 MW, mostly rooftop solar (31)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Heath Lane Academy, Heath Lanerooftop solar | rooftop solar | 0.3 | approved, not builtupdated Jul 2026 | Apr 2026 | granted Jun 2026 | Jul 2026 | Hinckley and Bosworth | 3.3 |
| Austral House, Coventry Roadrooftop solar | rooftop solar | 0.1 | approved, not builtupdated Jan 2023 | Nov 2022 | granted Jan 2023 | Jan 2023 | Harborough | 4.2 |
| Forest Roadbattery storage | battery storage | — | application submittedupdated Nov 2024 | Sep 2024 | — | Nov 2024 | Blaby | 4.6 |
| Leisure Centre Carlton Park, King Edward Avenuerooftop solar | rooftop solar | — | approved, not builtupdated Sep 2025 | Jul 2025 | granted Sep 2025 | Sep 2025 | Blaby | 5.0 |
| Park House Farm, Leicester Lanewind farm | wind farm | 0.8 | approved, not builtupdated Jun 2026 | Oct 2025 | granted Jun 2026 | Jun 2026 | Hinckley and Bosworth | 5.1 |
| Enderby Leisure Centre, Mill Lanebattery storage | battery storage | 0.2 | approved, not builtupdated Apr 2025 | Jan 2025 | granted Mar 2025 | Apr 2025 | Blaby | 5.4 |
| Feldspar Close - Plot N -Solar Panelsrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Aug 2025 | Jun 2025 | granted Aug 2025 | Aug 2025 | Blaby | 5.4 |
| Dorsey Way, Enderbyrooftop solar | rooftop solar | 0.7 | approved, not builtupdated Apr 2024 | Feb 2024 | granted Apr 2024 | Apr 2024 | Blaby | 6.1 |
| Enderby Road Industrial Estate, Enderby Roadbattery storage | battery storage | 0.2 | application submittedupdated Mar 2025 | Jan 2025 | — | Mar 2025 | Blaby | 6.6 |
| The Whittle Estate, Whetstonerooftop solar | rooftop solar | 0.4 | approved, not builtupdated Nov 2021 | Sep 2021 | granted Oct 2021 | Nov 2021 | Blaby | 6.8 |
| Leicestershire Constabulary, St Johnssolar farm | solar farm | 0.2 | approved, not builtupdated Aug 2024 | Jan 2024 | granted Jul 2024 | Aug 2024 | Blaby | 6.9 |
| Hinckley Leisure Centre, Argents Meadrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Oct 2024 | Aug 2024 | granted Aug 2024 | Oct 2024 | Hinckley and Bosworth | 7.0 |
| Centurion Way, Braunstone Townrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Dec 2021 | Aug 2021 | granted Oct 2021 | Dec 2021 | Blaby | 7.1 |
| Showroom Meridian East, Meridian Business Parkrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Feb 2026 | Nov 2025 | granted Jan 2026 | Feb 2026 | Blaby | 7.1 |
| Morrison Supermarkets, Cloverfieldrooftop solar | rooftop solar | 0.4 | approved, not builtupdated Nov 2022 | Oct 2022 | granted Nov 2022 | Nov 2022 | Hinckley and Bosworth | 7.2 |
| Burbage Houserooftop solar | rooftop solar | 0.3 | approved, not built may be out of dateupdated Aug 2023 | Apr 2023 | granted Jul 2023 | Aug 2023 | Hinckley and Bosworth | 7.3 |
| Unit F, Meridian Leisure Park, Braunstone Townrooftop solar | rooftop solar | — | approved, not built may be out of dateupdated Jun 2023 | May 2023 | granted Jun 2023 | Jun 2023 | Blaby | 7.8 |
| Saladworks, Kirby Muxloerooftop solar | rooftop solar | 0.6 | approved, not builtupdated Mar 2025 | Jan 2025 | granted Mar 2025 | Mar 2025 | Blaby | 7.8 |
| Meridian Leisure Park Solar Photovoltaics Arrayrooftop solar | rooftop solar | 0.2 | application withdrawnupdated Feb 2022 | Jan 2022 | — | Feb 2022 | Blaby | 7.9 |
| Dpd International Gateway, Logix Road Phase 1rooftop solar | rooftop solar | 0.8 | approved, not builtupdated Oct 2023 | Aug 2023 | granted Oct 2023 | Oct 2023 | Hinckley and Bosworth | 8.6 |
| Roman Avenue, Unit Arooftop solar | rooftop solar | 0.8 | approved, not builtupdated Mar 2024 | Jan 2024 | granted Mar 2024 | Mar 2024 | Blaby | 8.7 |
| E M E B Sports & Social Club, Nutts Lanesolar farm | solar farm | 0.3 | approved, not builtupdated Nov 2023 | May 2023 | granted Nov 2023 | Nov 2023 | Hinckley and Bosworth | 8.9 |
| Snippery Farm, Heath Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Jan 2026 | Sep 2025 | granted Dec 2025 | Jan 2026 | Hinckley and Bosworth | 9.0 |
| DPD International Gateway, Logix Road - Phase 2, Solar Panelsrooftop solar | rooftop solar | 0.5 | approved, not builtupdated Apr 2024 | Feb 2024 | granted Apr 2024 | Apr 2024 | Hinckley and Bosworth | 9.0 |
| Kirby Road Solar Panelsrooftop solar | rooftop solar | 0.5 | under constructionupdated Jan 2022 | Nov 2020 | granted Feb 2021 | Jan 2022 | Blaby | 9.2 |
| Park View Street - Micro Energy Systembattery storage | battery storage | 0.2 | approved, not builtupdated Jun 2026 | Apr 2026 | granted May 2026 | Jun 2026 | Leicester | 9.5 |
| Old Station Yard, Station Roadsolar farm | solar farm | 0.3 | application submitted may be out of dateupdated Jul 2024 | Jun 2024 | — | Jul 2024 | Harborough | 9.5 |
| Elms Farm Solar Farm & Battery Storagebattery storage | battery storage | — | approved, not built may be out of dateupdated Mar 2024 | Jun 2021 | granted Nov 2022 | Mar 2024 | Rugby | 9.5 |
| Granby Road Solar PV Panels & Air Source Heat Pumpsrooftop solar | rooftop solar | — | approved, not built may be out of dateupdated Dec 2021 | Dec 2021 | granted Mar 2022 | Dec 2021 | Leicester | 9.6 |
| Tesco Distribution Depot, Dodwells Roadrooftop solar | rooftop solar | — | approved, not builtupdated Oct 2024 | Aug 2024 | granted Sep 2024 | Oct 2024 | Hinckley and Bosworth | 9.7 |
| Hydes Lane, Stretton Baskervillebattery storage | battery storage | — | approved, not builtupdated Aug 2024 | Feb 2023 | granted Jul 2024 | Aug 2024 | Rugby | 10.0 |
Distance from the average position of the LE9 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 17 | 3 | 8 | 4 | 1 | 217 |
| Rooftop solar | 24 | 0 | 22 | 1 | 0 | 10.1 |
| Solar | 1 | 0 | 0 | 1 | 0 | 0 |
| Wind farm | 1 | 0 | 1 | 0 | 0 | 0.8 |
| Wind turbine | 2 | 0 | 0 | 1 | 0 | 0 |
| Battery storage | 10 | 2 | 5 | 3 | 0 | 501 |
MW in pipeline: pending, approved and under-construction capacity.
How Hinckley and Bosworth decides solar, wind and battery applications
| Applications | Hinckley and Bosworth | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 30 | 10,236 |
| Refused | 2 (7%) | 19% |
| Solar refused | 2 of 26 | 12% |
| Onshore wind refused | 0 of 3 | 45% |
| Battery storage refused | 0 of 1 | 16% |
| Median time from submission to decision | 13.1 weeks | 17.0 weeks |
| Appeals lodged / allowed | 1 / 1 | — |
All projects in Hinckley and Bosworth
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near LE9, 9 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.