Hangmans Hall Farm (35 MW solar farm)

Hangmans Hall Farm is a 35 MW solar farm project in Hinckley and Bosworth, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 8 July 2020; the record was last updated on 30 September 2020.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

35 MWsolar farm
refusedstatus in REPD
30 September 2020record last updated
Hinckley and Bosworthcouncil area

Planning timeline

DateStage
7 November 2019Application submitted
8 July 2020Refused by the planning authority

Project details

Technology
solar farm
Capacity
35 MW
Status (REPD)
refused
Record last updated
30 September 2020
Operator or applicant
Elgin Energy
Planning authority
Hinckley and Bosworth
Planning application reference
19/01256/FUL
Site area
61.9 ha
Address (REPD)
Hangmans Hall Farm, Twenty Acre Lane, Sutton Cheney, Nuneaton, Warwickshire
Council area (by location)
Hinckley and Bosworth
Time to decision
35 weeks
REPD reference
7382

Who decides

ApplicationsHinckley and BosworthUK
Decided applications (solar, wind, battery)3010,236
Refused2 (7%)19%
Solar refused2 of 2612%
Onshore wind refused0 of 345%
Battery storage refused0 of 116%
Median time from submission to decision13.1 weeks17.0 weeks
Appeals lodged / allowed1 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Kirkby Roadsolar farm23.5approved, not built2.2
Basin Bridge Farmsolar farm5operational4.4
Hall Farm Solar Farm (Newbold Verdon)solar farm5operational4.7
Hinckley Road Solar Farmsolar farm40approved, not built5.6
Stoneshollow Solar Farmsolar farm49.9approved, not built6.5
Hill Farm Solar Parksolar farm20application submitted6.9
Heath Road, Bagworth Solar Farmsolar farm21.5application submitted7.0
Normanton Energy Reservebattery storage500approved, not built7.1
Horiba Mira, Mira Drivesolar farm7operational7.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.591, -1.3745).