Basin Bridge Farm (5 MW solar farm)

Basin Bridge Farm is a 5 MW solar farm project in Hinckley and Bosworth, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 31 March 2016; the record was last updated on 15 December 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
15 December 2016record last updated
Hinckley and Bosworthcouncil area

Planning timeline

DateStage
24 September 2015Application submitted
18 February 2016Planning permission granted
18 February 2016Construction started
31 March 2016Operational

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
15 December 2016
Operator or applicant
Sun Farming UK
Planning authority
Hinckley and Bosworth
Planning application reference
15/00828/FUL
Site area
10.0 ha
Address (REPD)
Basin Bridge Farm, Basin Bridge Lane, Stoke Golding, Nuneaton
Council area (by location)
Hinckley and Bosworth
Time to decision
21 weeks
REPD reference
5643

Who decides

ApplicationsHinckley and BosworthUK
Decided applications (solar, wind, battery)3010,236
Refused2 (7%)19%
Solar refused2 of 2612%
Onshore wind refused0 of 345%
Battery storage refused0 of 116%
Median time from submission to decision13.1 weeks17.0 weeks
Appeals lodged / allowed1 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Horiba Mira, Mira Drivesolar farm7operational3.0
Elms Farm - Hinckley Solar Farm & Battery Storagesolar farm49.9approved, not built4.3
Hangmans Hall Farmsolar farm35refused4.4
Weddington Roadbattery storage49.9approved, not built4.6
Kirkby Roadsolar farm23.5approved, not built5.5
Lychgate Lane, Aston Flamville Solar Farmsolar farm20under construction7.4
Hall Farm Solar Farm (Newbold Verdon)solar farm5operational9.0
Hinckley Road Solar Farmsolar farm40approved, not built9.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.5614, -1.4184).