Hall Farm Solar Farm (Newbold Verdon) (5 MW)

Hall Farm Solar Farm (Newbold Verdon) is a 5 MW solar farm project in Hinckley and Bosworth, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 8 December 2015; the record was last updated on 18 July 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
18 July 2016record last updated
Hinckley and Bosworthcouncil area

Planning timeline

DateStage
17 July 2014Application submitted
3 June 2015Planning permission granted
7 September 2015Construction started
8 December 2015Operational

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
18 July 2016
Operator or applicant
Push Energy/ NextEnergy Solar Fund (NESF)
Planning authority
Hinckley and Bosworth
Planning application reference
14/00660/FUL
Site area
20.1 ha
Address (REPD)
Hall Farm, Main Street, Newbold Verdon, LEICESTER, LE9 9NL
Council area (by location)
Hinckley and Bosworth
Time to decision
46 weeks
REPD reference
1991

Who decides

ApplicationsHinckley and BosworthUK
Decided applications (solar, wind, battery)3010,236
Refused2 (7%)19%
Solar refused2 of 2612%
Onshore wind refused0 of 345%
Battery storage refused0 of 116%
Median time from submission to decision13.1 weeks17.0 weeks
Appeals lodged / allowed1 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Heath Road, Bagworth Solar Farmsolar farm21.5application submitted2.3
Stoneshollow Solar Farmsolar farm49.9approved, not built2.5
Lindridge Farmsolar farm5operational2.8
Crown Farmsolar farm6operational4.0
Hangmans Hall Farmsolar farm35refused4.7
Kirkby Roadsolar farm23.5approved, not built5.2
Hinckley Road Solar Farmsolar farm40approved, not built5.8
Desford Solar Farmsolar farm5operational6.1
Tower Hayes Farmsolar farm5operational6.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.6303, -1.3482).