Energy Projects Near You

Stoneshollow Solar Farm (49.9 MW)

Stoneshollow Solar Farm is a 49.9 MW solar farm project in Hinckley and Bosworth, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 16 August 2022, not yet built; the record was last updated on 23 September 2022. REPD records the planning permission as expiring on 16 August 2025, but the project holds a Contracts for Difference award (AR5), so construction may have started. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWsolar farm
approved, not builtmay be out of datestatus in REPD
23 September 2022record last updated
Hinckley and Bosworthcouncil area

REPD records the planning permission as expiring on 16 August 2025, but the project holds a Contracts for Difference award (AR5), so construction may have started.

Planning timeline

DateStage
22 November 2021Application submitted
16 August 2022Planning permission granted
16 August 2025Permission expired

Project details

Technology
solar farm
Capacity
49.9 MW
Status (REPD)
approved, not built
Record last updated
23 September 2022
Operator or applicant
JBM Solar Projects Limited
Planning authority
Hinckley and Bosworth
Planning application reference
21/01395/FUL
Site area
106.8 ha
Address (REPD)
Church Farm, Washpit Lane, Barlestone, Nuneaton
Council area (by location)
Hinckley and Bosworth
Time to decision
38 weeks
Contracts for Difference
AR5
REPD reference
9567

The scheme also includes battery storage, recorded separately in REPD (approved, not built).

Who decides

ApplicationsHinckley and BosworthUK
Decided applications (solar, wind, battery)3010,236
Refused2 (7%)19%
Solar refused2 of 2612%
Onshore wind refused0 of 345%
Battery storage refused0 of 116%
Median time from submission to decision13.1 weeks17.0 weeks
Appeals lodged / allowed1 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Crown Farmsolar farm6operational1.6
Hall Farm Solar Farm (Newbold Verdon)solar farm5operational2.5
Heath Road, Bagworth Solar Farmsolar farm21.5application submitted2.5
Lindridge Farmsolar farm5operational3.9
Tower Hayes Farmsolar farm5operational5.3
Hangmans Hall Farmsolar farm35refused6.5
Desford Solar Farmsolar farm5operational7.5
Kirkby Roadsolar farm23.5approved, not built7.5
Hinckley Road Solar Farmsolar farm40approved, not built8.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.6494, -1.3688).