Energy Projects Near You

Hill Farm Solar Park (20 MW)

Hill Farm Solar Park is a 20 MW solar farm project in Blaby, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application submitted on 19 November 2021, no decision recorded; the record was last updated on 23 December 2021. The application was submitted more than two years ago and is still shown as pending; it may have been decided since. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

20 MWsolar farm
application submittedmay be out of datestatus in REPD
23 December 2021record last updated
Blabycouncil area

The application was submitted more than two years ago and is still shown as pending; it may have been decided since. 32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided.

Planning timeline

DateStage
19 November 2021Application submitted

Project details

Technology
solar farm
Capacity
20 MW
Status (REPD)
application submitted
Record last updated
23 December 2021
Operator or applicant
Hill Farm Solar Ltd
Planning authority
Blaby
Planning application reference
21/1386/FUL
Site area
36.1 ha
Address (REPD)
Hill Farm, Earl Shilton Road, Thurlaston
Council area (by location)
Blaby
Name in REPD
Hill Farm - Solar Park
REPD reference
10161

Who decides

ApplicationsBlabyUK
Decided applications (solar, wind, battery)2210,236
Refused0 (0%)19%
Solar refused0 of 1712%
Battery storage refused0 of 516%
Median time from submission to decision8.4 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Normanton Energy Reservebattery storage500approved, not built0.3
Hinckley Road Solar Farmsolar farm40approved, not built1.3
Desford Road, Thurlastonsolar farm40approved, not built2.4
Enderby Storage, Redcomb Farmbattery storage49.9operational3.4
National Grid Enderby Substationbattery storage57operational3.9
Kirkby Roadsolar farm23.5approved, not built5.0
Desford Solar Farmsolar farm5operational5.6
Lindridge Farmsolar farm5operational6.4
Hall Farm Solar Farm (Newbold Verdon)solar farm5operational6.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.59, -1.2719).